GE Turbine Problems Hit Power Generation at 3 Pakistani Plants
Pakistan's Central Power Purchasing Agency's report shows that General Electric's 9HA-Class turbines produced only half of their capacity this August, according to Reuters. Power executives and government officials in the country said the GE turbines had operational issues like long outages and production delays. GE Turbine Problems: Bhikki Power Plant, Punjab, Pakistan The GE turbine problems affected three key plants – Bhikki of Punjab government and Balloki and Haveli Bahadur Shah of the federal government – with a total capacity of 3,600MW that are considered crucial to end load shedding within the ruling PMLN's 5-year term ending middle of 2018. Consequences For Pakistan: Pakistan's government is failing to deliver on its promise to end load-shedding this year because of serious issues with GE's 9HA-Class turbine. "It had terrible consequences because we lost a lot of power which would have come to the grid during the peak summer,"...