Pakistan Ramps Up Nuclear Power to Boost Low-Carbon Energy

Construction of 1,100 MW nuclear power reactor K2 unit in Karachi has been completed by China National Nuclear Corporation, according to media reports. A similar reactor unit K3 will add another 1,100 MW of nuclear power to the grid, bringing the total nuclear power installed capacity of Pakistan to 3,630 MW (12% of total power) by 2022.  Hualong One reactors being installed in Pakistan are based on improved Westinghouse AP1000 design which is far safer than Chernobyl and Fukushima plants.  In addition, Pakistan is also generating  9,389  MW (about 28% of total power) of low-carbon hydroelectric power in response to rising concerns about climate change.

Karachi Nuclear Power Plant (KANUPP):

With the placement of the outer containment shell, K2 is  now ready for containment and heat tests. It is scheduled to begin operations in 2020. It’s built using the Chinese HPR1000 technology, which features a dual containment design, with the outer containment providing additional protection for the primary containment.

Karachi Nuclear Power Plant K2 Unit Under Construction. Source: CNNC

KANUPP is Pakistan's first nuclear power plant where construction started in 1966 in Karachi. The plant was connected to the national grid on 18 October 1972. KANUPP, a pressurized heavy water reactor of 137 MW gross capacity was constructed by Canadian General Electric under a turnkey contract. In 1976, vendor support for spare parts and fuel was withdrawn. The PAEC undertook the task of indigenously manufacturing the required spare parts and nuclear fuel on an emergency basis and, since 1980, KANUPP has successfully operated using fuel manufactured by the PAEC, according to International Atomic Energy Agency (IAEA). Here is an except of IAEA's 2018 report on nuclear power in Pakistan:

"Despite the keen interest of Pakistan in building additional nuclear plants, it took more than two decades before the second nuclear power plant started construction. This delay was due to Pakistan’s lack of access to international nuclear technology coupled with a lack of indigenous industrial infrastructure. The construction of Pakistan’s second nuclear plant, C-1, a pressurized water reactor (PWR), was made possible in 1993 with the help of the China National Nuclear Corporation (CNNC). The plant was connected to the national grid on 13 June 2000 and has a gross capacity of 325 MW. A third nuclear power plant, C-2, with 325 MW gross capacity started commercial operation on 18 May 2011. The fourth unit, C-3, started commercial operation on 6 December 2016. It has a gross capacity of 340 MW and a similar plant, C-4, sited beside C-3, was connected to the grid on 25 June 2017. The first concrete pours to mark the start of construction of Karachi Coastal Power Project, a project containing two nuclear units, K-2 and K-3 (1100 MW each), based on an improved PWR design, were 20 August 2015 and 31 May 2016, respectively."


Pakistan Power Generation Fuel Mix. Source: Third Pole



International Energy Agency:

International Energy Agency (IEA) has recently warned that "steep decline in nuclear power would threaten energy security and climate goals". "With nuclear power facing an uncertain future in many countries, the world risks a steep decline in its use in advanced economies that could result in billions of tonnes of additional carbon emissions", the IEA has said.

Pakistan Among 31 Countries Operating Nuclear Power Plants


Nuclear is the second-largest low-carbon power source in the world today, accounting for 10% of global electricity generation. It is second only to hydropower at 16%, according to International Energy Agency (IEA). Pakistan nuclear plants are expected to generate 3,630 MW  (12% of total power vs 10% global average) by 2022.  Pakistan is also generating  9,389  MW (about 28% of total power vs 16% global average) of low-carbon hydroelectric power in response to rising concerns about climate change.

Nuclear Plant Safety Concerns:

Activists in Pakistan have raised serious concerns about potential risks from K2 and K3 plants to the population in Karachi. Are such concerns valid?

The worst nuclear disaster in the history of nuclear power generation was at Chernobyl in present day Ukraine. One of the key reasons was that the Chernobyl plant did not have the fortified containment structure common to most nuclear power plants elsewhere in the world. KANUPP K-2 and K-3 reactors have two containment shells: primary and secondary. It is noteworthy that Bhopal Union Carbide disaster was history's worst industrial disaster, far bigger in terms of human toll than the Chernobyl disaster.

China signed a technology transfer deal with the United States in 2006 that put the Westinghouse AP1000 reactor design at the “core” of its atomic energy program. Chinese reactor manufacturers also resolved to build advanced third-generation technology in their safety review after the 2011 Fukushima nuclear plant disaster.

Unlike Fukushima where underground emergency cooling system failed due to flooding, the Hualong One design stores water above the reactor that can be gravity-fed to keep it cool if the pumps fail in the event of meltdown. The Chinese HPR1000 reactors employ multiple redundant generators and cooling systems to lower meltdown risk.

Hydropower Generation:

The biggest and most important source of low-carbon energy in Pakistan is its hydroelectric power plants. Pakistan ranked third in the world by adding nearly 2,500 MW of hydropower in 2018, according to Hydropower Status Report 2019.  China added the most capacity with the installation of 8,540 megawatts, followed by Brazil (3,866 MW), Pakistan (2,487 MW), Turkey (1,085 MW), Angola (668 MW), Tajikistan (605 MW), Ecuador (556 MW), India (535 MW), Norway (419 MW) and Canada (401 MW).

New Installed Hydroelectric Power Capacity in 2018. Source: Hydroworld.com

Pakistan's Water and Power Development Authority (WAPDA) says commissioning of the 108-MW Golen Gol 2, 1,410-MW Tarbela 4th Extension and 969-MW Neelum Jhelum hydropower projects in 2018 boosted its hydroelectric generating capacity of 9,389 MW, an increase of 36% in just one year, according to Hydro Review. Hydropower now makes up about 28% of the total installed capacity of 33,836 MW as of February, 2019.   WAPDA reports contributing 25.63 billion units of hydroelectricity to the national grid during the year, “despite the fact that water flows in 2018 remained historically low.” This contribution “greatly helped the country in meeting electricity needs and lowering the electricity tariff for the consumers.”

Top 20 Countries by Newly Installed Hydropower Capacity. Source: IHA

Pakistan has the potential to generate 59,000 MW of hydropower, according to studies conducted by the nation's Water and Power Development Authority (WAPDA). Currently, it's generating only 9,389 MW of hydroelectric power, about 16% of the estimated potential. Media reports indicate that China is prepared to finance and build another 40,000MW capacity as part of the development of the Northern Indus Cascade region which begins in Skardu in Gilgit-Baltistan and runs through to Tarbela, the site of Pakistan’s biggest dam, in Khyber-Pakhtunkhwa province.

Pakistan has made only a small contribution to climate change through carbon emissions.  And yet, it counts among the dozen or so nations considered most vulnerable to its damaging effects. These include rising temperatures, recurring cycles of floods and droughts and resulting disruption in food production.

Summary: 

Construction of 1,100 MW nuclear power reactor K2 unit in Karachi has been completed by China National Nuclear Corporation, according to media reports. A similar reactor unit K3 will add another 1,100 MW of nuclear power to the grid, bringing the total nuclear power installed capacity of Pakistan to 3,630 MW (12% of total power) by 2022.  Hualong One reactors being installed in Pakistan are based on improved Westinghouse AP1000 design which is far safer than Chernobyl and Fukushima plants.  In addition, Pakistan is also generating  9,389  MW (about 28% of total power) of low-carbon hydroelectric power in response to rising concerns about climate change. One of the ways Pakistan can help reduce carbon emissions is by realizing its full nuclear and hydroelectric power potential by building more nuclear plants and dams. The development of the Northern Indus Cascade region to generate 40,000MW of hydropower is a significant part of this effort.

Related Links:

Haq's Musings

South Asia Investor Review

Nuclear Power in Pakistan

Recurring Cycles of Drought and Floods in Pakistan

Pakistan's Response to Climate Change

Massive Oil and Gas Discovery in Pakistan: Hype vs Reality

Renewable Energy for Pakistan

Digital BRI: China and Pakistan Building Fiber, 5G Networks

LNG Imports in Pakistan

Growing Water Scarcity in Pakistan

China-Pakistan Economic Corridor

Ownership of Appliances and Vehicles in Pakistan

CPEC Transforming Pakistan

Pakistan's $20 Billion Tourism Industry Boom

Riaz Haq's YouTube Channel

PakAlumni Social Network

Comments

Riaz Haq said…
Special instruction issued for promotion of Solar Energy, Net-Metering

https://www.thenews.com.pk/latest/490951-special-instruction-issued-for-promotion-of-solar-energy-net-metering

Power Division has issued special instructions to all DISCOs for promoting and further easing installation of net-metering in order to provide opportunity to all electricity consumers to curtail their monthly electricity bills besides optimal utilization of solar potential of the country.

The instructions were issued on Friday during one-point agenda on net-metering meeting of Central Power Purchasing Agency (CPPA).

As per the latest instructions, all the DISCOs have been directed to establish one window for interested net-metering electricity consumers. The appointment of focal persons will in this regard be ensured besides their active engagement on targets assigned by the Power Division.

Each officer at operational level will be assigned targets of net-metering which will be properly monitored. These targets and their results will count for greater points during their assessment for promotion and other benefits.

All the DISCOs are further directed to ensure proper briefing of consumers during open katcheris by the respective Superintending Engineers, XEN and SDOs.

All the DISCOs will also run a comprehensive awareness campaign for educating the consumers regarding benefits of net-metering.

The meeting while emphasizing the importance of net-metering in order to tap the solar energy potential of the country, also underscored the need to extend all out facilitation to the consumers by the DISCOs.

It was noted that although the rules and regulation for net-metering are adequate, however, the practical steps taken by DISCOs are not enough to promote it in order to fully and optimally utilize the potential.

It was further directed to strictly monitor all targets in this regard.

Earlier, the meeting was informed that a total of around 900 MW solar panels have been imported in the country. There are 1,190 electricity consumers with a cumulative capacity of 26MW who have installed net-metering so far.

Riaz Haq said…
#Pakistan added 500MW of #solar power in 2018. #Asia topped with new installations, despite declines in top three markets (#China, #India and #Japan). China alone accounted for around 45% of global additions, but this was down from nearly 54% in 2017. https://www.evwind.es/2019/06/21/photovoltaic-cumulative-capacity-increased-approximately-25-to-at-least-505-gw/67686

Photovoltaic capacity increased to 505 GW
June 21, 2019 reve
The annual global market for solar photovoltaics (PV) increased only slightly in 2018, but enough to surpass the 100 GW level (including on- and off-grid capacity) for the first time. Cumulative capacity increased approximately 25% to at least 505 GW; this compares to a global total of around 15 GW only a decade earlier. igher demand in emerging markets and in Europe, due largely to ongoing price reductions, compensated for a substantial market decline in China that had consequences around the world.

Despite the single-digit growth rate of the global market in 2018, solar PV has become the world’s fastest-growing energy technology, with gigawatt-scale markets in an increasing number of countries.

Demand for solar PV is spreading and expanding as it becomes the most competitive option for electricity generation in a growing number of markets – for residential and commercial applications and increasingly for utility projects – even without accounting for the external costs of fossil fuels.
Eleven countries added more than 1 GW of new capacity during the year, up from 9 countries in 2017 and 7 countries in 2016, and markets around the world have begun to contribute significantly to global growth. By the end of 2018, at least 32 countries had a cumulative capacity of 1 GW or more, up from 29 countries one year earlier.
There are still challenges to address in order for solar PV to become a major electricity source worldwide, including policy and regulatory instability in many countries, financial and bankability challenges, and the need to integrate solar PV into electricity markets and systems in a fair and sustainable manner.

-----------------

Turkey followed, installing 1.6 GW for a total of 5.1 GW, already surpassing the national target for 2023. However, Turkey’s additions were down 37% relative to 2017 due to several factors, including uncertainties regarding national support schemes, issues related to land acquisition, permission and financing, as well as delays as project developers await further cost reductions.
Others in Asia to add capacity included Chinese Taipei (almost 1 GW), driven by a FIT and a target of 20 GW by 2025, as well as Pakistan (0.5 GW) and Malaysia (0.4 GW).
Riaz Haq said…
#Chinese #investment in #renewables triples under Belt and Road initiative (#BRI). Biggest recipient of Belt & Road investment was #Pakistan, where equity investments from #China accounted for 36.8% of the country’s new #wind capacity from 2014 to 2018. https://www.pv-magazine.com/2019/07/30/chinese-investment-in-renewables-triples-under-belt-road-initiative/

A report by Greenpeace has found in the five years since China announced the continent spanning ‘One Belt, One Road’ infrastructure plan, investment in Belt & Road countries has supported 12.6 GW of wind and solar power generation capacity. That is almost three times the 450 MW that came online in the territories before 2014. The initiative has also supported 68 GW of new coal capacity.

A study published this week by environmental charity Greenpeace found China’s Belt & Road Initiative has led an investment surge in energy infrastructure in the regions covered by the plan – particularly south and Southeast Asia – over the past five years.

According to the NGO, Chinese equity investment in solar, wind and coal power projects in south and Southeast Asia rose 1,370% during 2014-2019, compared to the previous five years.

The Greenpeace study shows 12,622 MW of wind and solar power generation capacity along the Belt & Road route was supported by Chinese equity investment, alongside 67.9 GW of coal capacity. Some 93% of the wind and solar investment – and 94% of the coal projects – went to south and Southeast Asia.

“Solar now presents a serious rebuttal to any pattern of Chinese overseas pro-coal bias,” said Liu Junyan, a Beijing-based climate and energy campaigner with Greenpeace East Asia. “Chinese investors’ ratio of coal to solar is now the same at home and abroad – both are still six-to-one coal, unfortunately, but I’m amazed to see what five years of equity investment in solar made possible.”


Of the 12.6 GW of renewables capacity to be funded by Chinese investment, 1.7 GW has already been installed – 1.2 GW of it solar. For PV, that represents a 280% increase in capacity funded through equity investment. At the end of last year, a further 10.8 GW project pipeline in Belt & Road countries had received equity investment from Chinese companies. The largest single recipient of Belt & Road related investment was Pakistan, where equity investments from China accounted for 36.8% of the country’s new wind capacity from 2014 to 2018.

The Belt & Road route covers a wide corridor along the former overland Silk Road and maritime Spice Route from China to Europe across Asia and includes central Asia, the Middle East, parts of Africa and southern Europe.

For renewables and coal, equity in projects is the primary form of investment. Greenpeace pointed out for coal the rise of renewables represents a serious threat.

“Equity ties Chinese investors to overseas coal projects for the long run,” said Wang Yan, of Greenpeace East Asia. “And there’s a slew of financial, environmental and regulatory risks on the horizon. But the equity model also gives Chinese enterprises license to invest in a variety of projects. It’s Beijing’s job to educate Chinese companies on coal risks and the potential of equity investment in renewables before a series of bad investments put a stink on the whole Belt & Road.”
Riaz Haq said…
Experts see space for ample growth in Pakistan’s civil nuclear energy sector

https://www.thenews.com.pk/print/508871-experts-see-space-for-ample-growth-in-pakistan-s-civil-nuclear-energy-sector

Brigadier Kazmi said Pakistan’s nuclear energy sector had contributed to the socio-economic uplift of the county and there was ample space for growth in this industry.

“The nuclear energy sector has been playing a very important role in power generation, minerals exploration, developing high-yield stress-tolerant crops, cancer treatment, designing and fabrication of industrial plants and equipment and human resource development for many years.”

He said Pakistan is one of the countries in the world that have operated a complete nuclear fuel cycle and is amongst 30 countries that have nuclear power plants in operation. “Pakistan has a remarkable experience in safe and secure operation of nuclear power plants. We have the expertise and the ability to supply items, goods and services for a full range of nuclear applications for peaceful uses.”

Pakistan has established four agriculture centres that use energy for optimisation of important crop varieties, development of better methods for conservation of inputs and products, in addition to maximum use of innovation technologies.

Brigadier Kazmi further stated that safety and security were an integral part of any nuclear program and vital for saving humans from technology and ensuring that humans did not misuse the technology.

Vice Chancellor Professor Dr Khalid Mahmood Iraqi said that we all are convinced that Pakistan is a responsible state and uses its nuclear energy for peaceful purposes.

“When we have a glance at the rapidly growing population of Pakistan and even the faster growing power needs of this population, one can convincingly understand that it is impossible to meet these needs by use of the conventional methods and techniques for power generation. Our nuclear plants are significantly (not sufficiently though) helping power requirements.”

He expressed that Pakistan became a nuclear power 21 years ago and acquiring this status was the only choice because the government and the people well understood the geo-political scenario and the history of its relations with the neighbours.

Prof Iraqi said that Pakistan consistently stands by its policy to develop an efficient and consumer- centric power generation, transmission and distribution system that meets the needs of its people and supports the country’s economy in a sustainable and affordable manner.

He further said that the main concern of our nuclear plants has been to completely eliminate power loadshedding, reducing the cost of electricity to affordable level for the citizens, and increasing revenue collection to support its economy.

During the recent years, according to the vice chancellors, our industries have faced a significant setback due to power deficit, which has ultimately placed a negative impact on the life of a considerable portion of our population in social and economic forms.

The nuclear power for peaceful use is our highly-deserved priority, he added. Professor Dr Zafar Nawaz Jaspal, Director Politics and International Relations, Quaid-e-Azam University, Islamabad, observed that whenever there is high alert at the boarders, Pakistan faces propaganda of being an irresponsible nuclear state despite the fact that Pakistan has never violated the Geneva Convention and always respects all international humanitarian laws and agreements.

He observed that Pakistan’s nuclear program is much better than its neighbouring country. The nuclear energy could be used for the benefit of civilians or to gain military power, he said, adding that Pakistan always gives priority to peaceful use of nuclear energy over the race to nuclear weapons.

]
Riaz Haq said…
Huge #Pakistan Thar mine shows #power of #coal. In Cholistan Desert, Pak is building a #solar farm which will expand to 8X the size of New York’s Central Park. Gov't has the ambition to generate 60% of its power from #renewable sources in about a decade https://www.japantimes.co.jp/news/2019/08/09/asia-pacific/science-health-asia-pacific/mile-wide-open-mine-pakistan-shows-coal-wont-go-away/

In the flat scrubland of Pakistan’s scorching Thar Desert, hundreds of workers have been toiling for two years in the vast open pit of the Sindh Engro Coal Mining Co. Taking three-hour breaks during the hottest part of the day and living in a makeshift village of shipping containers, they are digging for fuel to sustain a $3.5 billion power project. So far they have scraped away about 500 feet (150 meters) of Aeolian sand, dirt and coal to create a hole a mile (1.6 km) wide.

Far to the north, in the Cholistan Desert, lie the skeletal beginnings of a solar farm that is supposed to expand to eight times the size of New York’s Central Park. It is the largest solar project in Pakistan, where the government has recently announced an ambitious plan to generate 60 percent of its power from renewable sources in about a decade.

If these grand developments in the desert suggest that coal and solar are in a close-run contest, they are not. Before 2016, Pakistan had a single coal-fired plant. It now has nine, supplying 15 percent of the nation’s electricity, with another four under construction. Solar power provides about 1 percent of energy needs and is getting a tiny sliver of investment compared with what is going into coal. Solar and other renewables may someday eliminate Pakistan’s dependence on coal, but that day is probably decades away.

And that is fine as far as Akhtar Mohammad is concerned. “Coal is good. It’s cheap,” he said at his roadside kiosk in Port Qasim on the outskirts of Karachi, where air pollution is “among the most severe in the world,” according to the nongovernmental Pakistan Air Quality Initiative. “There is a lot of smoke and bad air already. We need electricity — any fuel, it doesn’t matter.”

Mohammad’s pragmatism sums up the planet’s quandary. “Coal is the absolute No. 1 cause of carbon emissions globally and the leading driver of climate change,” said Tim Buckley, Sydney-based director of energy finance studies at the Institute for Energy Economics & Financial Analysis.

But though wealthy nations may be able to afford to wean themselves off coal, which is one of the biggest contributors of greenhouse gases, in countries where electricity is scarce, unreliable or unaffordable, local politics often takes precedence over economics: Coal remains the cheap fallback.

Dozens of coal plants in Asia
Especially in Asia, dozens of coal plants have come on line in recent years or are in the planning stages — with a normal lifetime of almost half a century. In South and Southeast Asia, coal burning is expected to increase about 3.5 percent a year for the next two decades, according to the International Energy Agency. Globally, the IEA predicts, coal demand won’t peak until 2040. And that may be optimistic. Forecasts often assume governments will choose the cheapest option based on optimum efficiency while factoring in environmental constraints and the falling cost of solar and wind power.

Coal consumption won’t decline as significantly as people think, says Shirley Zhang, Wood Mackenzie Ltd.’s principal Asia-Pacific coal analyst. On the one hand, annual global sea-borne coal trade probably peaked last year at 980 million tons. On the other hand, from now until 2040, it will decline by only 20 million tons, she says. Despite the rise of renewables, the roll call of governments adding coal-fired plants includes four of the world’s five most populous nations: China, India, Indonesia and Pakistan.

Riaz Haq said…
How #cleantech can help power #Pakistan's #green #revolution. Pakistan is 8th-most affected country from #ClimateChange #CPEC must include #renewables in its integrated energy planning in Pakistan https://www.weforum.org/agenda/2019/09/how-cleantech-can-help-power-pakistans-green-revolution/ via @wef

Pakistan has been the 8th-most affected country when it comes to climate change. Although the government recognizes that vulnerability, there is a lot of room for forming an effective adaptation plan.

Pakistan has set aside 7.6 billion rupees ($47 million) for addressing climate change in its 2019-2020 budget. This will be spent on new initiatives and ongoing schemes including climate-resilient urban settlements, the establishment of a Geomatic Centre for Climate Change and of a Pakistan Water, Sanitation & Hygiene Strategic Planning and Coordination Cell, as well as sustainable land management projects to combat desertification. Pakistan planted a billion trees in the northwestern Khyber Pakhtunkhwa region, and there is a commitment to plant 10 billion trees over the next five-to-eight years.

But governments cannot achieve climate change targets by themselves. Increasing public-private partnerships are required. Global trends in innovation have led to the advent of ‘cleantech’ - technological innovations with sustainable aims, such as reducing our carbon footprint, meeting the demands for clean energy, cleaner air and water, producing healthy food for our ever-growing population, and the optimal utilization of finite resources.


--------

The government should provide basic funding for research by providing grants to universities and other researchers, and offering tax credits on private sector research. In Pakistan, which has many energy projects in the pipeline through the China Pakistan Economic Corridor, the government should include renewables in its integrated energy planning, in order to attract investment at scale in cleantech, and should include cleantech targets in primary legislation, provide green financing options and most importantly phase out fossil fuel subsidies. Its focus must now be on greening projects across all sectors throughout the country.

Share
Farooq T. said…
For the month of August 2019, 47.7% of Pakistan's electricity came from zero-carbon emissions sources (hydroelectricity, nuclear, wind, and solar), according to data from the National Electric Power Regulatory Authority.
Riaz Haq said…
#Pakistan government inks deals for 560 MW of fresh #WindEnergy. The move is in line with the country’s 30% national #renewables goal by Year 2030. https://www.renewablesnow.com/news/pakistani-govt-inks-deals-for-560-mw-of-fresh-wind-676632/

Pakistan’s Alternative Energy Development Board (AEDB) on Friday signed contracts with the developers of projects that will see the country expand its wind power capacity by 560 MW.

The government agency, which is tasked with promoting renewables installation in Pakistan, has inked implementation and guarantee direct agreements with independent power producers (IPPs) regarding 11 projects. The move is in line with the country’s 30% national renewables goal by 2030 and efforts to cut dependence on fossil fuel imports. The new capacity is expected to lead to the production of over 1.8 billion kWh of clean power per year, AEDB said.

Six of the schemes will be supported by the International Finance Corp (IFC), which on Friday signed agreements to finance the so-called Super Six project portfolio with USD 450 million (EUR 406.9m) in debt. Those power plants, with a combined capacity of 310 MW, will be installed in the Jhimpir wind corridor in Sindh province and will be able to generate enough electricity to cover the annual needs of 450,000 homes while offsetting around 650,000 tonnes of carbon dioxide (CO2) emissions annually, IFC said in a separate statement. It will provide some USD 86 million in funds from its own account and USD 234 million mobilised from other lenders.

The 11 projects are expected to become operational by 2021.

(USD 1.0 = EUR 0.904)
Riaz Haq said…
IRENA Pegs #Pakistan’s Total #RenewableEnergy Capacity By 2018-End At Over 13,000 MW, With #Solar Contributing 12% Or More Than 1,500 MW. Target: 30% of installed capacity to be #renewable by 2030. #cleanenergy #ClimateChange http://taiyangnews.info/markets/pakistans-cumulative-solar-capacity-tops-1-5-gw/

At the end of 2018, the cumulative installed solar energy capacity of Pakistan had reached 1,568 MW, increasing from 742 MW at the end of 2017, representing an addition of over 800 MW in a single year. These statistics are published in the International Renewable Energy Agency’s (IRENA) annual report, Renewable Capacity Statistics 2019.

The report tracks renewables growth of several countries starting from 2009. For Pakistan it means solar power capacity of 4 MW in 2009 has now grown to 1.5 GW, accounting for 12% of out of 13 GW of total renewable energy capacity of the country in 2018.

Globally, a total of 171 GW of new renewable energy capacity was installed in 2018, growing 7.9% annually, of which 84% came from wind and solar alone. In concrete terms, solar added 94 GW of new capacity with Asia accounting for 64 GW, while wind grew by 49 GW.

According to an April 2018 Renewables Readiness Assessment report of IRENA, Pakistan does not have a clear renewable energy target, which the agency says is a must to ‘translate political will into a language that can be understood by investors’.

The World Wind Energy Association reported on April 2, 2019 that the new government in the country under Prime Minister Imran Khan plans to increase the share of renewable energy in total power generation to 30% by 2030, from wind, solar and biomass, and additionally 30% from large-scale hydropower. It would be a 26% points increase from the current renewables share of 4%. Pakistan is working on its Renewable Energy Policy 2019 whose guiding principles have been approved by the government’s Cabinet Committee on Energy (CCoE).

As per January 2017 directives issued by the National Electric Power Regulatory Authority (NEPRA) of Pakistan, the country should be moving towards a competitive bidding process for utility scale solar and wind power plants, something that’s yet to take place.

In a December 2018 report, the Institute for Energy Economics and Financial Analysis (IEEFA) wrote that the country could reach 12.4 GW of total installed solar power capacity by 2029-30, provided the government came up with clearly defined targets for long-term renewable energy policy (see IEEFA Suggests 30% RE For Pakistan By 2030).

Riaz Haq said…
New #IAEA Collaborating Centre in #Pakistan for #Nuclear #Technology. Partnership with PIAES in 3 key areas: Modelling and simulations with verification and validation capabilities, experimental nuclear #engineering, and education and training. https://www.iaea.org/newscenter/news/new-iaea-collaborating-centre-in-pakistan-to-assist-in-applications-of-nuclear-technologies#.Xg_bUF1cpQ8.twitter

With a cooperation agreement signed today, the IAEA has designated the Pakistan Institute of Engineering and Applied Sciences (PIEAS) as an IAEA Collaborating Centre to support Member States on research, development and capacity building in the application of advanced and innovative nuclear technologies.

Islamabad-based PIAES is one of Pakistan’s leading public research university in engineering and nuclear technology and a major nuclear research facility of the Pakistan Atomic Energy Commission.

“I cannot emphasize enough the importance of education and training for building the capacity of Member States in this field,” said IAEA Deputy Director General Mikhail Chudakov, Head of the Department of Nuclear Energy, at the signing ceremony at the Agency’s Vienna headquarters. “Through this network, the Agency encourages scientific studies and cooperation across Member States, making the centres a key IAEA cooperation mechanism.”

This partnership with PIAES is based on a holistic and multidisciplinary approach in three key areas: modelling and simulations with verification and validation capabilities, experimental nuclear engineering, and education and training. Member States will strengthen their capacities in reactor technology design, nuclear-renewable hybrid energy systems, and reactor numerical modelling and simulations.

“We are first and foremost a university, so academics and research and development is at the heart of what we do,” underlined Nasirmajid Mirza, Rector of PIAES. “It will be rewarding to further build and develop capacity in nuclear technology and non-electric applications of nuclear energy and teach it to those who want to learn.”

IAEA Collaborating Centres
Through the Collaborating Centres network, Member States can assist the IAEA by undertaking original research and development and training relating to nuclear science, technologies and their safe and secure applications. With the newly designated Collaborating Centre PIAES in Pakistan, there are now 43 active Collaborating Centres worldwide, with ongoing discussions in several countries to establish new Centres.
Riaz Haq said…
IAEA Collaborating Centre
Pakistan Institute of Engineering and
Applied Sciences (PIEAS)


https://www.iaea.org/sites/default/files/19/09/collaborating-centres.pdf


Collaboration on
Research, development and capacity building for
multidisciplinary application of advanced and innovative
nuclear technologies
Objectives
• Contribute to creation of new and support of the IAEA ongoing activities on
the advancements and innovation in reactor designs and their applications
• Develop new experiments at nuclear engineering facilities to create new
benchmark databases in support of on-going and planned IAEA
programmatic activities in reactor simulation and modelling and
multipurpose applications of advanced and innovative reactor designs, and
the IAEA HOPS part-task simulator web-platform
• Co-organize/host workshops, training courses and seminars, including
development of training materials and IAEA relevant publications
• Host researchers and IAEA fellows wishing to conduct joint research
and/or training in supporting capacity building for multidisciplinary
applications of advanced and innovative nuclear reactor systems
(electrical and non-electrical applications, hybrid energy systems, large
power reactor design and their abilities for isotope production)
• Sharing the experience of PIEAS with IAEA Member States on laboratory
experiments, numerical modelling and nuclear education
• Providing experts to IAEA in the relevant areas of work
Main Activities of the Collaboration
• Research and development in the advancements and innovation of reactor
designs and reactor numerical modelling and simulations
• Contribute to technical development, system analysis, and optimization of
nuclear-renewable hybrid energy systems
• Conduct new experiments at the research facilities creating new
experimental data for the validation of computer codes for modelling of
advanced and innovative reactor designs and contribute to the IAEA
HOPS platform in the development, validation and verification of the parttask simulators
• Train professionals on advanced and innovative reactor designs with the
use of IAEA basic principle simulators and contribute to the creation of
new IAEA relevant publications
• Develop educational and training materials for hands-on capacity building
Related IAEA Projects
All projects under IAEA’s sub-programme on Technology Development for
Advanced Reactors and Non-Electric Applications (1.1.5) and specific projects
under IAEA’s sub-programmes on Research Reactors, Nuclear Knowledge
Management, and NA-Division of Physical and Chemical Sciences.
Designation period
2019-2023
Riaz Haq said…
World Bank to provide additional $700m for #Pakistan’s Dasu #hydropower project. It will produce 4,320 MW of #electricity at $0.03/kWh (down from current $0.08/kWh) and the power generated will mostly be supplied during the summers when the demand is high

https://www.power-technology.com/news/world-bank-to-provide-700m-more-for-pakistan-hydropower-project/

The World Bank has agreed to provide additional financing for the Dasu Hydropower Stage I project in Pakistan.

The $700m loan will fund the transmission line for the first phase of the Dasu hydropower plant. Situated along the main Indus River, the plant will have an installed capacity of 2,160MW.

The International Bank for Reconstruction and Development (IBRD) will finance the project.

The Dasu Hydropower Stage II expansion plan is expected to increase the project’s capacity to 4,320MW.

World Bank Pakistan country director Illango Patchamuthu said: “Pakistan’s energy sector is aiming to move away from high-cost and inefficient fossil fuels towards low-cost, renewable energy to power the national grid.

“Along with reforms in the tariff structure, the Dasu hydropower project will result in fewer imports of fossil fuels, alleviating the stress on the country’s current account balance.”

The Dasu hydropower station will produce electricity at $0.03/kWh and the power generated will mostly be supplied during the summers when the demand is high.

The low-cost, renewable energy will supply affordable electricity to households as well as the manufacturing and agriculture sectors.

Currently, the average cost of electricity generation in the country stands at $0.08/kWh.

World Bank projects task team leader Rikard Liden said: “The Dasu hydropower plant has a low environmental footprint and is considered to be one of the best hydropower projects in the world.

“It will contribute to reducing Pakistan’s reliance on fossil-fuels and producing clean renewable energy.”
Riaz Haq said…
#WorldBank approves $700m for #renewableenergy in #Pakistan. #Dasu dam will produce 2,160 MW in phase 1 to 4,320 MW in phase 2. #Hydrolectric #power to help reduce imports of fossil fuels, alleviating the stress on the country’s current account balance. https://tribune.com.pk/story/2188561/3-world-bank-approves-700m-help-pakistan-generate-renewable-energy/

The World Bank on Wednesday approved $700 million additional financing to help Pakistan generate low cost, renewable energy to provide affordable electricity to millions of users.

The World Bank is also working with the federal and provincial governments to deal with the coronavirus pandemic as the confirmed coronavirus cases soar past 2,000.

The additional financing will be used to complete the first phase of the Dasu Hydropower project. It will install 2,160 megawatts capacity along the Indus River.

Stage two will double the installed capacity to 4,320 megawatts – making it the largest hydropower plant in the country.

“Pakistan’s energy sector is aiming to move away from high-cost and inefficient fossil fuels towards low-cost, renewable energy to power the national grid,” said Illango Patchamuthu, World Bank Country Director for Pakistan.

“Along with reforms in the tariff structure, the Dasu Hydropower Project will result in fewer imports of fossil fuels, alleviating the stress on the country’s current account balance.”

The project will help lower the overall cost of energy generation in the country, which will benefit millions of energy users by making electricity more affordable for households, as well as the manufacturing and agricultural sector.

The powerplant will provide its electricity particularly in the summer to reduce blackouts when the demand is higher.


“The Dasu hydropower plant has a low environmental footprint and is considered to be one of the best hydropower projects in the world,” said Rikard Liden, Task Team Leader for the project.

“It will contribute to reducing Pakistan’s reliance on fossil-fuels and producing clean renewable energy.”

The Dasu hydropower plant will produce electricity at $0.03/kWh compared to Pakistan’s current cost of electricity generation of $0.08/kWh.

This investment will help Pakistan pave its way into becoming an upper middle-income country by 2047.
Riaz Haq said…
#Pakistan awards $5.8B contract for #dam construction to consortium of #Chinese and #Pakistani companies. #diamerbhashadam will store 6.4 million acre feet (MAF) of #water and produce 4,500 MW of clean #electricity.$1.03B for social programs around the dam http://v.aa.com.tr/1839628

Islamabad on Wednesday granted a contract worth 442 billion Pakistani rupees ($5.85 billion) to a consortium of Chinese and Pakistani companies for construction of a major dam to cope with the country's growing energy requirements.

The contract was signed at a ceremony in the capital Islamabad between the Water and Power Development Authority (WAPDA), and a joint venture of Power China, and Frontier Works Organization – a subsidiary of Pakistan’s Army – for construction of a diversion system, main dam, and access bridge of Diamer-Basha dam, apart from a 21 megawatt hydropower project.

Amir Bashir Chaudhry, chief executive officer of the project, and Yang Jiandu of Power China signed the agreement on behalf of WAPDA and the joint venture respectively, according to a statement by the Water and Power Ministry.

WAPDA has already awarded a consultancy contract of the project to Diamer Basha Consultants Group (DBCG) worth 27.182 billion rupees ($168.8 million). The consultancy agreement includes construction design, construction supervision, and contract administration of the Diamer-Basha Dam project, the statement added.

The development came a day after Prime Minister Imran Khan announced the start of construction of the much-awaited dam in northern Pakistan.

The $14 billion dam, to be constructed on the River Indus in the northern Gilgit-Baltistan region, which borders China, is set to produce 4500MW of affordable electricity, said the statement.

"The 6.4 MAF [million acre foot] water storage capacity of the dam will reduce the current water shortage in the country of 12 MAF to 6.1 MAF," the statement said, adding that it will also add 35 years to the life of Tarbela Dam – one of the two major dams in Pakistan – by reducing sedimentation.

Some 78.5 billion rupees ($1.03 billion) will be spent on social development of the area around the dam, mainly on resettlement of the population.

"It will also be a major source of flood mitigation and save billions worth of damages caused by floods each year," the statement said.

Earlier, Asim Saleem Bajwa, special assistant to the prime minister on information, called the announcement "historic."

"Announcing to start construction of Diamer Bhasha dam today is a historic news for all generations of Pakistan, a huge stimulus for our economy, create 16,500 jobs, generate 4500 MW hydel power, and irrigate 1.2 million acre agriculture land," he tweeted on Monday.
Riaz Haq said…
#Pakistan’s 969 MW-Neelum Jhelum #Hydropower Project achieved yet another milestone, as its contribution to the National Grid crossed 8 billion units mark and earned Rs80 billion revenue. #lowcarbon #RenewableEnergy - UrduPoint

https://www.urdupoint.com/en/pakistan/neelum-jhelum-hydropower-project-earns-rs-80-923385.html

In terms of revenue, Neelum Jhelum Hydropower Project has yielded more than Rs 80 billion of hydel electricity into the National Grid with efficient operation of the project by Neelum Jhelum and WAPDA engineers and staff under tiring conditions, said a press release.

The project, satisfactorily meeting the design capacity energy production, achieved this land mark despite the fact that the shelling by India from across the Line of Control during July and October 2019 interrupted the working at the project, which forced evacuation of the Chinese workers from the project site and continue to be afflicted by COVID-19 pandemic.

Neelum Jhelum Hydropower Project, one of the engineering marvels, has been constructed in a very difficult mountainous terrain and being 90 percent of the project underground.

The project is comprised of a weir (dam), underground water way system of 52-kilometer long tunnels, an underground power house and a switch yard. The project, having four generating units of 242.25 MW capacity each, started electricity generation with commissioning of its first unit in April 2018. The project attained its maximum installed generation of 969 MW on August 14, 2018 with commissioning of its all four units.

It is worth mentioning here that Neelum Jhelum generated up to 1040MW on April 9, 2019 beyond installed capacity of 969 MW, which reflects the efficiency of its electro-mechanical equipment, the turbines in particular. Now-a-days, the project has been running on full load i.e. 969MW because the required quantum of water is available due to high-flow season.


Riaz Haq said…
GE bags #Pakistan #hydro deal. #Dasu #Hydroelectric project will be done in 2 stages. First stage consists of installing a 2,160MW hydropower plant on the Indus River, which could be expanded to 4,320MW in a second phase.- reNews - #RenewableEnergy News https://renews.biz/60392/ge-bags-pakistan-hydro-deal/#.XsQ3ku6M540.twitter

GE Renewable Energy, in consortium with Powerchina Zhongnan Engineering, has been selected by Pakistan Water and Power Development Authority (WAPDA) to supply six Francis turbines and generators for stage one of the new Dasu hydropower plant in Pakistan.



The 2.2GW Dasu hydropower project is among the largest power generation projects in the country.



“The plant will help generate clean electricity, ushering in a new era of socio-economic potential and development in remote areas,” GE said in a statement.

The project will be completed in two stages. The first stage consists of installing a 2160MW hydropower plant on the Indus River, which could be expanded to 4320MW in a second phase.



This project is part of the Vision 2025 Programme launched by WAPDA in 2001 and the Government of Pakistan’s Power Policy 2013.



Once commissioned in 2026, the Dasu hydropower plant will power around four million households in Pakistan.



GE Renewable Energy’s hydro business is responsible for the design, supply, supervision, installation, and commissioning of the new turbines and generators, as well as the control and protection systems. GE Grid Solutions will provide the Generator Circuit Breaker.



WAPDA chairman Lt Gen Muzzammil Hussain (Retd) said: “The project is vital to add a major quantum of hydroelectricity to the national grid in order to minimise reliance on expensive thermal generation and lower the power tariff.”



President and chief executive of GE Renewable Energy Hydro Pascal Radue added: “We are proud to start this new collaboration with WAPDA and will support them to develop clean and sustainable electricity in Pakistan.



"We are also glad to be part of this new hydropower project that will facilitate access to electricity in remote areas.”

Riaz Haq said…
#China ignores #India over world's highest Diamer-Bhasha #dam project in #Pakistani #Kashmir. #Islamabad gets #Beijing funds for joint venture opposed by #Delhi. It will generate 4,500 MW of #power & store 8 million acre-feet of #water. #RenewableEnergy

https://asia.nikkei.com/Spotlight/Belt-and-Road/China-ignores-India-over-dam-project-in-Pakistani-Kashmir


Riaz Haq said…
#Pakistan's Suki Kinari #hydroelectric power project unaffected by #COVID19. 19.5% work on the 874 MW dam project completed on Kunhar River with an investment of
US $ 1.963 billion under the umbrella of #CPEC. #China #renewableenergy https://www.app.com.pk/progress-of-suki-kinari-power-project-remains-unaffected-during-covid-19-asim-bajwa/ via @appcsocialmedia

Special Assistant to Prime Minister on Information and Broadcasting General (retd) Asim Saleem Bajwa Wednesday said work on the Suki Kinari hydal power project was in full swing as progress on the project remained unaffected due to COVID-19.
In a tweet, Asim Bajwa who is also Chairman, China Pakistan Economic Corridor Authority (CPECA) said, 19.5 percent work on the 874 MW power project had been completed.
He said the project was being established at Kunhar River with an investment of
US $ 1.963 bn under the umbrella of China Pakistan Economic Corridor.
He informed that the project had so far created 4,250 job opportunities and
after completion it would help reducing cost of electricity.
“Bringing cost of electricity down is top priority of the government,” he added.
Riaz Haq said…
#WorldBank approves US $700m for 4,320 MW Dasu #hydropower project in #Pakistan. Loan will be used to build transmission line and complete the 2,160MW first phase of the plant. Total project cost: cost US $4.2 billion.
https://constructionreviewonline.com/2020/04/world-bank-approves-us-700m-for-4-32gw-dasu-hydropower-project-in-pakistan/ via @Construction Review Online

The World Bank has approved US $700m grant to finance the construction of the 32GW Dasu hydropower project in Pakistan. The hydroelectric power plant which is being built on the Indus River, approximately 7km upstream of the Dasu town, Kohistan, Khyber Pakhtunkhwa; is being implemented by Pakistan’s Water and Power Development Authority (WAPDA).

The World Bank’s additional financing will be used to construct the transmission line and complete the 2,160MW first phase of the plant. The entire project is estimated to cost US $4.2bn.

Upon completion, the Dasu hydropower plant will become the largest of its kind in the country, generating low-cost, renewable energy to power millions of users. The hydropower plant is expected to come online in 2023.

World Bank Pakistan country director Illango Patchamuthu said that Pakistan’s energy sector is aiming to move away from high-cost and inefficient fossil fuels towards low-cost, renewable energy to power the national grid. “Along with reforms in the tariff structure, the Dasu Hydropower Project will result in fewer imports of fossil fuels, alleviating the stress on the country’s current account balance,” he said.

In addition to providing most of the clean electricity during the summer months, the Dasu hydropower plant is expected to contribute to the socioeconomic development in Dasu and surrounding areas of the Upper Kohistan District of Khyber Pakhtunkhwa Province.

Furthermore, World Bank Task Team Leader Rikard Liden added that the Dasu hydropower plant has a low environmental footprint and is considered to be one of the best hydropower projects in the world. “It will contribute to reducing Pakistan’s reliance on fossil- fuels and producing clean renewable energy,” he affirmed.
Riaz Haq said…
Deal worth $2.4 billion signed with #China for 1,124 MW Kohala #hydropower project in #AJK. Signatories include Three Gorges Corporation, the government of Azad Jammu and #Kashmir (AJK) and #Pakistan’s Private Power and Infrastructure Board (PPIB). #CPEC

Furthermore, another hydroelectric power project – the 102MW Gulpur project – located at Poonch River, Kotli district of AJK met the commercial operation date on March 10, 2020.

https://tribune.com.pk/story/2233400/2-deal-worth-2-4b-signed-kohala-power-project/

PPIB Managing Director Shah Jahan Mirza briefed PPIB on the status of upcoming IPPs, explaining that various projects may experience delay in achieving critical milestones primarily due to Covid-19 and project sponsors were requesting support from PPIB in combating the situation. The board, while considering the intensity of the matter, allowed extension in the validity of Letter of Support/ financial close date for the 1,124MW Kohala hydroelectric power project.

It also agreed to provide support for Thar coal-based power generation projects in getting required extension in the backdrop of the global pandemic.

Agreeing on a proposal, the board with the consensus of all provinces and AJK allowed extension in the validity of Letters of Interest in respect of 640MW Mahl, 450MW Athmuqam and 82.25MW Turtonas-Uzghor hydroelectric power projects for accommodating these IPPs under the Indicative Generation Capacity Expansion Plan.

Moreover, the board was apprised that PPIB had started processing small hydroelectric power projects for the first time, therefore, standard security package agreements including the implementation agreement (IA) were required to be in place.

PPIB had prepared a standard draft of IA, which needed approval, the board was told. A committee of the board has been constituted to review the draft of the standard IA for small hydroelectric power projects for its onward submission to the ECC for consideration and approval.
Riaz Haq said…
#China's Goldwind books 50-MW #WindEnergy turbines order in Jhimpir, #Sindh, #Pakistan in an area identified as a “wind corridor” with 1000 MW of wind power capacity installed. Golwind expects to install 150 MW of turbines in Pak in coming years #renewable https://www.renewablesnow.com/news/goldwind-books-50-mw-turbine-order-in-pakistan-701129/

China’s Xinjiang Goldwind Science & Technology Co Ltd (HKG:2208) said it has recently received an order to supply 50 MW of turbines for the ACTII wind project in Pakistan.

Goldwind is set to deliver 20 units of GW 121-2.5MW high temperature model turbines to local wind project developer ACT Wind (Pvt) Ltd, the Chinese manufacturer said.

The ACTII project is sited in Jhimpir, Sindh province, in the area identified as a “wind corridor” and with around 1 GW of wind power capacity installed, according to Goldwind.

ACT Wind is the Chinese company's repeat customer, after previously purchasing Goldwind turbines for the first ACT wind project. The 30-MW ACT wind farm has been operating for about four years.

Goldwind expects to install 150 MW of turbines in Pakistan over the coming years and bring its total installed capacity in the country to 477 MW.

In November 2019, Goldwind signed a contract with Power Construction Corporation of China Ltd (SHA:601669), also known as PowerChina, to equip the 50-MW Gul Ahmed wind project in Pakistan. It has also secured the contract for the Artistic II wind farm project in the country, the company said.
Riaz Haq said…
#Pakistan #Uranium exploration in Bannu, Kohat approved. The country is investing heavily for the development of #nuclear #medicine and radiation therapy hospitals and equipment including the #cancer fighting centres.- Pakistan - DAWN.COM

https://www.dawn.com/news/1563546

The government has approved work for exploration of uranium in Bannu basin and Kohat plateau at an estimated cost of Rs926.03 million and allocated Rs200m for Atomic Energy Commission’s project in the budget for fiscal year 2020-21.

The country is investing heavily for the development of nuclear medicines and radiation-related hospitals and equipment including the cancer fighting centres.

Currently, there are 18 ongoing development projects of the commission and Rs23.09bn has been allocated for these projects in the new budget. None of the projects have any foreign funding, either in the shape of grants or loans.

These projects include uranium exploration in the Dera Ghazi Khan area of Punjab for which Rs140m has been allocated in the budget though the project’s total cost is Rs794.9m.

For the cancer hospital NORI Islamabad, which is expected to be completed by the end of June 2021, Rs1.23bn has been allocated. For each of the Bahawalpur Institute of Nuclear Medicine & Oncology (BINO) and Karachi Institute of Radiotherapy and Nuclear Medicine, Rs125m has been allocated in the federal budget.

Government plans to invest heavily in nuclear medicines

Similarly, Rs280m has been allocated for Gilgit Institute of Nuclear Medicine, Oncology and Radiotherapy and Rs500m for Gujranwala Institute of Nuclear Medicine and Radiotherapy. Both the centres are expected to become operational next year.

As the country is also investing in the nuclear power projects, Rs18bn has been allocated for units 1 and 2 of the Karachi coastal power projects and Rs1.5bn has been allocated for the research reactor-3 of 10 megawatts.

The 3D printing facility being established in Islamabad has been allocated Rs97.43m in 2020-21.

However, only Rs10m has been allocated for nuclear fuel enrichment plant and Rs21m for the nuclear power fuel testing project in the next budget, indicating that work has been stalled or slowed down at these projects.

Other projects, where the pace of work has apparently slowed down, includes the fuel fabrication plant and the seamless tube plant for which the government has allocated Rs42m and Rs32m, respectively.

The new development budget has allocated Rs100m for studies related to the development of nuclear power plants and Rs140m for survey of mineral resources.

There are two development projects for Pakistan Nuclear Regulatory Authority (PNRA), including the establishment of national radiological emergency coordination centre in Karachi, Islamabad and Mianwali, with the final allocation of Rs199.18m. The other PNRA project is related to enhancing the capacity of the regulator for oversight against vulnerabilities of cyber threats with the allocation of Rs150m.
Riaz Haq said…
Pakistan Govt signs tripartite agreement for 1124 MW $2.4 billion Kohala Hydro Power Project in Azad #Kashmir , the largest private #hydropower project (IPP) for the country. #China’s Three Gorges Power Company will build and own it - Dunya News


https://dunyanews.tv/en/Pakistan/551382-Govt-signs-tripartite-agreement-for-1124-MW-Kohala-Hydro-Power-Project-

Kohala Hydropower Project has reached a historic tripartite agreement, with an investment of 2.4billion dollars in the energy sector.

Prime Minister Imran Khan, Federal Ministers, Chinese Ambassador Yao Jing and others witnessed the ceremony.

Prime Minister Imran Khan addressed the signing ceremony of Kohala Hydropower Project Agreement and said that prices have gone up due to generation of electricity from imported fuel. Generating electricity from oil also affects the environment. Therefore government has focused on clean energy instead of imported fuel. Leading Three Gorges Company will develop Kohala Hydel project. The project will create employment opportunities in Azad Kashmir, he added.

He said the project has been the largest investment of $2.4 billion and Pakistan has great potential to generate electricity from water.

Earlier, retired Lieutenant General Asim Saleem Bajwa, chairman of the China Pakistan Economic Corridor Authority (CPECA), described it as a historic day in a tweet and said that it has been the largest investment from an IPP of $ 2.4 billion towards the energy sector.

The Chairman CPEC Authority said that with the clear direction of the Prime Minister to expedite the work on the Economic Corridor projects, all parties have worked hard for this day.
Riaz Haq said…
#Pakistan PM #ImranKhan: 'Will build biggest dam in Pakistan's history'. Kicks off construction work at #DiamerBhashaDam to store 6.4 MAF, irrigate 1.2 M acres of farm land, generate 4500 MW Hydel power, add 16,000 jobs in steel/cement/construction sectors https://www.dawn.com/news/1569151

Prime Minister Imran Khan on Wednesday vowed to build the "biggest dam in Pakistan's history" after kicking off construction work at the Diamer-Bhasha Dam project, adding that the project will also benefit the people living in Gilgit-Baltistan (GB).

The prime minister made the remarks while addressing a public gathering in Chilas.

Earlier, the PM had visited the site of the dam along with Chief of Army Staff Gen Qamar Javed Bajwa and Federal Minister for Water Resources Faisal Vawda, where they were briefed on the mega project.

---
The premier, during his address, vowed that with this project, the government was going towards building the "biggest dam in Pakistan's history".

"This will be our third big dam. China has made around 5,000 big dams, but have a total of about 80,000 dams. From this you can gauge the massive mistakes we have made in the past.

"The decision to build this dam was taken 50 years ago. There can be no better site for constructing a dam, it is a natural dam. Forty, 50 years ago this was decided, and work on the project has begun today. This is one of the biggest reasons why we haven't progressed."

The premier maintained that the government will now move towards building more dams on rivers, which will lessen pressure on foreign exchange and allow Pakistan to generate its own fuel.

He added that generating electricity from water instead of furnace oil or coal will also prevent negative impacts of global warming and climate change. "The benefits are dual. We won't have to import fuel and it won't affect our climate negatively."

Imran said that the project would also generate job opportunities for people living in the region. "I am familiar with GB and have visited Chilas on multiple occasions in the past 30 years. I am well aware how much the area depends on tourism and how much they need tourism during the summer months."

He said that he will speak to the chief minister to prepare standard operating procedures (SOPs) for resurrecting the tourism industry that has been severely impacted by the Covid-19 pandemic.

"We can learn from the world, tourism is slowly resuming. It won't be the same as it was before the pandemic hit, but we can start opening it slowly and start developing SOPs for it," he said, adding that help will also be extended by the National Command and Control Centre (NCOC) in this regard.

The premier added that the project was a huge opportunity for the people of Chilas and GB. Addressing the people of GB, he said: "We didn't increase your budget out of obligation. It is our government's policy to prioritise those areas that have been left behind.

"Thus far, our development has been restricted to a few cities. We will be left behind until we spend on uplifting less-developed areas."

Therefore, the government is investing in GB, merged districts and Balochistan, he said. He concluded his speech by congratulating the people of GB. "Time will prove that this dam will change the fortune of the people of GB, especially those living in Chilas."

The premier had began his speech by stressing that nations only progress when they think of the future and when they invest in their resources, uplifting those segments of society that have been left behind.

"The decisions made in the 90s to generate electricity using imported furnace oil affected our current account deficit. When there is pressure on foreign exchange, [the country's] economic conditions start deteriorating."
Riaz Haq said…
#CPEC Re-Emerges In #Pakistan With Flurry Of Major #China Deals: 2 #hydropower projects costing $3.9 billion, and another to revamp Pakistan's colonial-era railways for $7.2 billion -- the most expensive #Chinese project yet in Pakistan. https://www.ndtv.com/world-news/belt-and-road-re-emerges-in-pakistan-with-flurry-of-china-deals-2263687 via @ndtv

China's Belt and Road program has found new life in Pakistan with $11 billion worth of projects signed in the last month, driven by a former lieutenant general who has reinvigorated the infrastructure plan that's been languishing since Prime Minister Imran Khan took office two years ago.
The nations signed deals on June 25 and July 6 for two hydro-power generation projects costing $3.9 billion in the Pakistan-occupied Kashmir region, and another to revamp the South Asian nation's colonial-era railways for $7.2 billion -- the most expensive Chinese project yet in Pakistan.

Khan's government appointed Asim Saleem Bajwa last year to run the China-Pakistan Economic Corridor Authority, which oversees more than $70 billion in projects from power plants to highways.

He also joined Khan's cabinet in late April, becoming one of more than a dozen former and current military officials in prominent government roles as the army expands its influence in the country.

The Chinese financing has helped rid Pakistan of an electricity deficit that left exporters unable to meet orders and major cities without electricity for much of the day. Still, the implementation of some investments appeared to stall since Khan came to power, with no new projects announced in 2018 and very few in 2019.

Since Chinese President Xi Jinping launched the initiative in 2013, the World Bank estimates about $575 billion worth of energy plants, railways, roads, ports and other projects have been built or are in the works across the globe. Its progress has slowed recently, dogged by accusations that China is luring poor countries into debt traps for its own political and strategic gain.

"The reality is that much of CPEC, like the Belt and Road more broadly, has been paralyzed," said Jonathan Hillman, a senior fellow at the Center for Strategic and International Studies in Washington, referring to the China-Pakistan Economic Corridor. Pakistan "is a flagship for China's Belt and Road, so the need to show progress is even more important."

In a tweet last month, Bajwa said some detractors had given the "false impression" that CPEC had been slowed. Not only has the pace of work on projects picked up recently, but a great deal of ground work has been done to launch phase two of the project that also includes special economic zones to lure Chinese manufacturers, agriculture, science, technology and tourism, he wrote.

"The prime minister pushed very hard on this," said Abdul Razak Dawood, Khan's adviser on commerce and investments said by phone. "We feel that we have to get more and more hydro in our energy mix."

A spokesman in Bajwa's office said he was not immediately available to comment.

Little Progress

Pakistan's army is already responsible for securing every single Beijing-funded project scattered across the country, from the mountains near the Chinese border to the desert in Gwadar where the Chinese operate a port. Its role has become even more important following terrorist attacks on three Chinese-related projects in the past year.

"There is no doubt that PM Khan's arrival slowed the pace of CPEC projects," said Mosharraf Zaidi, a senior fellow at Islamabad-based think tank, Tabadlab, and a former principal advisor to the foreign ministry. "The renewed energy and approval we are now seeing is almost entirely likely due to the chairperson having settled in, and being added to Prime Minister Khan's cabinet."
Riaz Haq said…
#UN #SDGs: #Pakistan has achieved ‘Climate Action’ goal 10 years ahead of the deadline, a recognition of Pakistan’s commitment to fighting #climatechange, but also an endorsement of the success of #ImranKhan govt's initiatives. #ClimateAction #PTI | https://tribune.com.pk/article/97098/how-successful-has-pakistans-climate-change-fight-been

According to the Sustainable Development Report 2020, an annual global assessment of countries’ progress towards achieving the United Nations led Sustainable Development Goals (SDG), Pakistan has achieved the ‘Climate Action’ SDG ten years ahead of the deadline. This is not only a recognition of Pakistan’s renewed commitment to fighting climate change, but also an endorsement of the success of numerous environmental protection initiatives launched by the government.

Traditionally, climate change has not been a key agenda item in Pakistan’s public discourse which over time has resulted in a gross underestimation of the gravity of the situation. Therefore, it is important to begin by recognising that climate change is a very real threat to Pakistan’s long-term prosperity and survival. According to the Global Climate Risk Index, Pakistan was the 5th most affected country by the impact of climate change during the twenty-year period from 1999-2018. The Index used a weighted score, based on climate change mediated death toll and loss to the economy (in purchasing power parity terms), to calculate a Climate Risk Index (CRI) score which was then used to rank countries.

With rising Greenhouse Gas (GHG) emissions and a dwindling forest cover, Pakistan’s annual mean temperature is estimated to rise by three to five degrees Celsius by the end of the century. Already, cities such as Turbat and Nawabshah are witnessing record high temperatures, confirming the worst fears of climate change scientists. The rising temperatures will over time result in rapid melting of the glaciers that feed Pakistan’s rivers, as well as in a projected 60 cm rise in the sea level by the year 2100. Coupled with a high variability in precipitation, these changes are expected to lead to an increase in the frequency and intensity of extreme weather events such as heat waves, floods, droughts and tropical storms, jeopardising Pakistan’s agriculture, economy, water and food security, as well as the health of the country’s inhabitants.

Despite the seriousness of the threat, Pakistan’s fight against climate change did not really take off until 2013. The origins of the new-found fervor can be traced back to the Billion Trees Afforestation Project (BTAP), popularly known as Billion Tree Tsunami. Through BTAP, over a five-year period the Pakistan Tehreek-e-Insaf (PTI) government in Khyber Pakhtunkhwa restored 350,000 hectares of forestland employing a combination of natural regeneration and planned afforestation. As a result, the province’s forest cover increased by about five per cent and half a million green jobs were created. The initiative received global acclaim after a third-party audit by the World Wildlife Fund (WWF) confirmed nearly 85% average survival of the plantations. It exceeded the province’s Bonn Challenge commitment and was hailed as a “true conservation success story” by the International Union for Conservation of Nature (IUCN). Not only did the successful execution of BTAP make climate change a significant issue of public interest in Pakistan, it also served to put the country on the map in the global fight against climate change.

Since 2018, Pakistan’s fight against climate change has picked up further pace. There has been a discernible shift in the government’s priorities with the emergence of an overarching “Green Growth Agenda” that has informed several initiatives across the country. With an aim to replicate the success of BTAP on a national level, ...
Riaz Haq said…
#DiamerBhashaDam, world's tallest dam at 272 meters, will change #Pakistan's destiny by addressing its #energy & #water problems. Located in #GilgitBaltistan, it will store 6.4 million acre-feet of water, generate 4,500 MW of cheap #renewable #electricity https://global.chinadaily.com.cn/a/202007/20/WS5f14f269a31083481725a98f.html

Project, to be ready in 2028, expected to meet water, energy needs in Gilgit-Baltistan region

A new mega project in northern Pakistan is expected to meet both water and energy needs of the region, according to officials and experts.

Work on the construction of Diamer Bhasha Dam near Chilas, a city in the Diamer district in the Gilgit-Baltistan region, has started.

"Diamer Bhasha Dam is set to change the destiny of Pakistan by addressing its energy and irrigation problems," Faisal Vawda, Pakistan's federal minister for water resources, said. "It's Pakistan's lifeline."

The dam's reservoir will be 272 meters in height, and it is said to be the tallest roller compact concrete dam in the world.

Roller compacted concrete is a special blend of concrete that has the same ingredients as conventional concrete but in different ratios, and with a partial substitution of fly ash for Portland cement. This reduces thermal loads on the dam and reduces chances of thermal cracking.

The dam has a proposed spillway with 14 gates and five outlets for flushing out silt. The diversion system comprises two tunnels and a diversion canal. It will also include the construction of powerhouses.

Asim Saleem Bajwa, chairman of China-Pakistan Economic Corridor Authority, said the dam will generate 4,500 megawatt of hydroelectric power.

It was a historic moment as Prime Minister Imran Khan kicked off the construction work on Diamer Bhasha Dam, he said. "Around 16,000 jobs will be created during the construction of the dam."

Imran Khan officially launched the construction work on Wednesday, with Pakistan's Chief of Army Staff Qamar Bajwa by his side.

The biggest

"Diamer Bhasha Dam will be the biggest dam in Pakistan's history," the prime minister said while addressing the public during the launch. "The dam will benefit the country both economically and environmentally, especially the people of Gilgit-Baltistan," he said.

The multibillion-dollar project is estimated to be completed in 2028. It is a multipurpose project that will be used for water storage, flood mitigation, irrigation and power generation.

"This is no ordinary project. There is a reason why both Pakistan's prime minister and the army chief were present at the site for the project launch. It will have an impact on Pakistan's economy, security and politics," said Ahmed Quraishi, a senior fellow at Project Pakistan 21, an independent research organization based in national capital Islamabad.

Feather in the cap

It is another feather in the cap for the Chinese engineers who are known for undertaking challenging international projects, he said.

The project is being jointly constructed by Power China and Pakistan's Frontier Works Organization.

The Water and Power Development Authority of Pakistan approved the award of civil works for construction of the dam and the 21-MW Tangir Hydropower Project to the joint venture partners.

The two companies signed a contract in June with a local company for the construction of the diversion system, main dam and access bridge as well as the hydropower project.

"We are grateful to our all-weather friend China for its support in the construction of the mega project," said Faisal Vawda, the water resources minister.

Quraishi said the technical specifications of the project suggest it will be something that engineers worldwide will be studying due to the region's terrain. "China's experience in the dam construction is unparalleled," he said.
Riaz Haq said…
(Bloomberg) — As developed nations turn away from coal-fired power, Chinese funding has helped the dirtiest fossil fuel take off in Pakistan.


https://financialpost.com/pmn/business-pmn/china-push-sees-coal-fired-generation-rise-to-record-in-pakistan


Coal’s surge in the South Asian nation is symbolic of the difficult choice that the region’s developing countries face as they seek affordable energy to support economic growth while trying to limit chronic air pollution. Asian demand is expected to support the commodity as its usage drops in most of the developed world in a transition to cleaner or renewable energy sources.

Is Canada's real estate forecast too optimistic?



Pakistan’s coal-fired power generation jumped 57% to a record in the fiscal year through June, according to data from the government’s National Electric Power Regulatory Authority. Coal accounted for about a fifth of total output, backed by supplies from the country’s first coal mine in its Thar region, developed as part of China’s Belt and Road plan.

Coal is set to expand further as China pushes funds into building more power plants in the country and mines to feed them. Pakistan is one of the flagship markets for China’s Belt and Road initiative, with more than $70 billion of projects including coal and liquefied natural gas fired power plants helping the nation end decades of electricity shortfalls.


“China has been cutting back on coal at home but it has no compunction about using coal in things that it funds outside of China,” said James Dorsey, a senior fellow at the S. Rajaratnam School of International Studies in Singapore. “Chinese can be willing but they need a partner to go along with them. In this case it’s the Pakistani government.”

Belt and Road progress has slowed recently with overseas energy spending last year dropping to the lowest in a decade, dogged by accusations that China is luring poor countries into debt traps for its own political and strategic gain. China’s President Xi Jinping has publicly urged more clean energy as part of the program, and the plan found new life in Pakistan recently with an agreement to build two hydro-power generation projects.

Until 2016, Pakistan had just one coal-burning power plant. It now has at least nine and more are in the making. The first target of these plants has been to replace expensive fuel oil-based generation facilities that burdened the nation’s economy with heavy costs and pollution.

The rise in coal power has come because of supplies from the Thar coal mine, Power Ministry spokesman Zafar Yab Khan said. The country will balance rising coal use with more renewable energy and its coal plants will use low-emissions technology, he said.

Read: A Hole in Pakistan’s Desert Shows Why Coal Won’t Go Away

With the shift to coal, average generation costs dropped 11% during the fiscal year, according to data from Karachi-based brokerage Arif Habib.

“Pakistan has increased coal-based generation to make it its new base to replace its previous expensive fuel oil-powered power plants,” said Tahir Abbas, head of research at Arif Habib. “This has also helped bring down the power prices, energy import bill and increase the share of an indigenous energy source.”
Riaz Haq said…
Hot testing completed at #Pakistan’s 1100 MW #Karachi 2 #nuclear power plant. Construction of Karachi 2 began in August 2015, followed by Karachi 3 in May 2016. Outer containment dome of Karachi 3 was installed in August 2020. Nuclear Engineering


https://www.neimagazine.com/news/newshot-testing-completed-at-pakistans-karachi-2-8128090


Unit 2 at Pakistan’s Karachi Nuclear Power Plant has completed hot functional tests, according to China National Nuclear Corporation (CNNC), which is constructing two units (2&3) at the plant.

Karachi 2 is the first overseas unit to use China's Hualong One technology. The thermal testing will be followed by nuclear fuel loading, grid connection and power generation.

The tests, lasting several weeks, includes simulating nuclear power plant operations to verify reliability of the main equipment and systems under thermal conditions before the reactor is loaded with nuclear fuel. They were completed on 4 September, CNNC said. Cold functional tests were completed at Karachi 2 in December 2019.

After the completion of hot tests, the Karachi 2 came close to the stage of physical launch, the message says.

Construction of the 1100MW Hualong One reactor Karachi 2 began in August 2015, followed by Karachi 3 in May 2016.

The outer containment dome of the Karachi 3 was installed at the end of August, CNNC said.
Riaz Haq said…
#COVID19 Lessons for #Pakistan #Climate Advisor: For every $ invested in nature, you get 9 dollars back.
Imbalances between humans & natural world have led to zoonotic #pandemics. Pakistan's billion tree project has helped the economy and the community.
https://www.weforum.org/agenda/2020/09/two-things-nature-taught-us-during-covid-pakistan-climate-advisor/

Pakistan's climate minister and advisor Malik Amin Aslam says nature has taught us two key things during the coronavirus pandemic.

Firstly, if you treat it badly, it will strike back. And secondly, if you treat it well, there are many benefits.

The minister for climate change, who also advises Pakistan's prime minister, was speaking on the first day of the World Economic Forum's Sustainable Development Impact Summit.

"When you start investing in nature, nature always pays you back," he said, referring to Pakistan's billion tree planting project, which has reaped dividends by creating jobs, engaging the community and helping develop a new economy.


He said his country's experience proved that for every dollar you invest in nature, you get nine dollars back.

"We don't have to come out of this pandemic on the same pathway that got us in there. You've seen the different world during this pandemic when humans have retreated. What has happened? You've seen the blue skies, the clean air that we've all built," he said, describing this as a positive opportunity.

Hanging in the balance

On the other hand, treating nature badly could lead to more difficulties down the line, the minister warned.

"The stark warning that nature has given to all of the world is that there are boundaries and nature works within certain limits and certain balances. And if we tried to tilt that balance, nature will strike back," he said.

The minister pointed to the fact that we are living in the middle of a zoonotic pandemic because humans have invaded the territory of animals as evidence of nature striking back.

Zoonotic diseases are those that jump from animals to humans. Rats, bats, monkeys and apes are among those more likely to spread zoonotic germs. Other illnesses and diseases that have been spread this way include Ebola, HIV, SARS and MERS, and Zika.

The UNEP has warned that human activity including urbanization and industrialized agriculture has laid the foundations for pandemics by causing biodiversity loss and environmental damage.

The coronavirus is now present in more than 200 countries, with more than 31 million global cases and almost one million global death, according to figures compiled by the Johns Hopkins University.
Riaz Haq said…
#Pakistan Pursues Big Action On #ClimateChange. Along with #trees planting, #PTI govt announced a new #ElectricVehicle policy this summer, and plans to get two-thirds of its #electricity from #renewable sources like #wind, #solar and #hydropower by 2030. https://www.npr.org/2020/09/29/916878679/with-glaciers-melting-and-temps-soaring-pakistan-pursues-big-action-on-climate-c?utm_campaign=storyshare&utm_source=twitter.com&utm_medium=social

On her first foray into tree planting, Laiba Atika forgot a key item — a shovel, which her mom later fetched.

But the 17-year-old is clear about why she is leading volunteers in the northern Pakistani city of Mardan to plant dozens of pine trees in a scrubby park.

"It's our duty as citizens," she says in formal English, "to implement actions that can make planet a better place to live in."

Atika's tree-planting drive is being replicated all over Pakistan, where the government aims to plant ten billion trees over five years with the help of local communities. The reforestation initiative is central to a wide-ranging plan the Pakistani government recently adopted to change practices and cut emissions that drive climate change.

Like most developing nations, Pakistan is not a big emitter of heat-trapping greenhouse gases. But developing countries suffer harm disproportionate to their historically low emissions. Climate-fueled extreme weather events, from floods to droughts, could displace or kill tens of thousands of people, straining government resources and threatening political stability.

That urgency has prompted some nations, such as Pakistan, to craft ambitious plans to reduce emissions, even as the world's second largest emitter, the United States, shrugs off serious climate action.

Pakistani Prime Minister Imran Khan "knows the implications of climate change and is willing to take the lead in putting Pakistan on a green trajectory," says Malik Amin Aslam, a senior climate change advisor to Khan and the leading proponent of the new policies.

Alongside tree planting, the government announced a new electric vehicle policy this summer, and plans to get two-thirds of its electricity from wind, solar and hydropower by 2030. "That is a genuine step up in ambition for renewable energy," said Simon Nicholas, an energy finance analyst who follows Pakistan at the U.S.-based Institute for Energy Economics and Financial Analysis.

But the problems that have long hobbled Pakistan threaten its new climate goals, too, environmental activists say. Plans are undermined by corruption and lax implementation, according to Afia Salam, an activist in Karachi. Environmentalists point to other ambitious policies the government announced since it took power, like a ban on plastic bags in Islamabad, which has gone widely ignored.

Khan's own broad-tent party, Pakistan Tehreek-e-Insaf, includes powerful business interests that have carved out loopholes for themselves from the climate policies.

"What Pakistan has done, despite resource constraint, is aspirational for many countries," Salam says. But, she adds, "there's so many conflicting interests within the party itself."

The world's fifth most populous country, Pakistan is one of the most vulnerable to global warming. Already, summer temperatures in its southern cities often surpass 120 degrees. Rainfall has grown more erratic, and in August, unprecedented monsoon rains drowned parts of Pakistan's largest city, Karachi, turning roads into rivers and killing dozens of people across the country.

Northern glaciers nestled in mountains are the country's main water source, and they are melting faster than ever. Highland communities now face occasional water shortages and flash flooding that sweeps away their lands. If the growth of global greenhouse gas emissions continues on its present trajectory, the water supply for Pakistan's 220 million people will be imperiled within 50 years, scientists say.
Riaz Haq said…
#Pakistan's 300 MW Chashma 4 #Nuclear Power Plant officially accepted. Chasnupp is home to two #Chinese-supplied 300 MWe PWRs as well: unit 1, in commercial operation since 2000, and unit 2, since 2011.: New Nuclear.
#electricity - World Nuclear News https://www.world-nuclear-news.org/Articles/Pakistans-Chashma-4-officially-accepted

Chashma unit 4 was connected to the grid on 29 June, 2017. The Chinese-supplied pressurised water reactor (PWR) is the second of two CNP-300 units to enter service at the site, following unit 3 which entered commercial operation in December 2016. The Chashma site - also referred to as Chasnupp - is home to two Chinese-supplied 300 MWe PWRs as well: unit 1, in commercial operation since 2000, and unit 2, since 2011.

For the final acceptance ceremony, held at Chashma on 23 September, CNNC set up video connections at construction subsidiary China Zhongyuan Engineering Company's headquarters in Beijing and at the Pakistan Atomic Energy Commission (PAEC) headquarters in Islamabad. Participants in the ceremony included PAEC Chairman Muhammad Naeem and CNNC President Gu Jun.

CNNC said China and Pakistan have maintained a strong partnership in the nuclear power sector since the two countries signed an agreement in 1986 to facilitate the transfer of civil nuclear technology.

Regarding future cooperation, Gu Jun said: "CNNC will, as always, assist Pakistan in the operation and maintenance of its plants, provide full-life and full-service services, and commit to providing clean, efficient and safe energy to the Pakistani people."

Pakistan also has a 125 MWe Canadian-supplied pressurised heavy water reactor, Karachi unit 1, which has been in commercial operation since 1972. Two 1161 MWe Chinese-supplied Hualong One (HPR1000) plants are under construction as units 2 and 3 of the Karachi plant. Construction of unit 2 began in 2015 and unit 3 in 2016. The units are scheduled for commercial operation in 2021 and 2022, respectively.

In November 2017, CNNC and PAEC signed a cooperation agreement on the construction of a Hualong One reactor as unit 5 of the Chashma plant.

Riaz Haq said…
#Pakistan Plants 500 Million New #Trees in Drive Against Climate Change. The #PTI government's countrywide $760 million reforestation drive is on track to plant more than three billion trees by mid-2023 to mitigate the effects of #ClimateChange.



https://www.voanews.com/south-central-asia/pakistan-plants-500-million-new-trees-drive-against-climate-change



Aslam noted the tree plantation program is also generating tens of thousands of new employment opportunities and is expected to create about 1.5 million jobs over the next three years when the government will have hit the target of nearly 3.3 billion trees.

“For every dollar you invest in nature, you get nine dollars back. So, you get jobs, you get local employment, you get (a) green economy going,” the minister told VOA.

“Even during the COVID era, we created 84,000 jobs for people who were out of jobs,” he added, referring to the coronavirus pandemic that hit Pakistan in February.

The outbreak prompted Prime Minister Imran Khan’s government to introduce nationwide lockdowns to curb the spread of the COVID-19 virus, which has infected at least 315,000 Pakistanis, and resulted in more than 6,500 deaths. New infections, however, have dramatically and steadily declined to several hundred a day since June, encouraging the government to lift all lockdowns.

Khan spearheaded a reforestation campaign, known as Billion Tree Tsunami, in the northwestern Khyber Pakhtunkhwa (KP) province, which his Pakistan Tehreek-e-Insaf (PTI) Party has been governing since 2013.

The four-year program restored 350,000 hectares of forests and degraded land, surpassing its 348,400 hectares commitment to the Bonn Challenge and winning Khan international praise for his climate change efforts.

The Bonn Challenge, established in 2011, calls for the restoration of 350 million hectares of deforested and degraded lands by 2030.

Billion Tree Tsunami program

The Billion Tree Tsunami program generated about 500,000 green jobs for men and women in poverty-stricken remote areas of the scenic Pakistani province. It has established a network of private tree nurseries and boosted local incomes.

The World Wildlife Fund-Pakistan (WWF-P), which monitored and audited the tree-planting effort in KP, reported that the project has been an environmental, economic and social success, with one of the highest survival rates of trees in the world, ranging from 75% to more than 80%.

Officials at the International Union for Conservation of Nature-Pakistan (ICUN-P) hailed the initiative as “a true conservation success story.”

Khan launched the Ten Billion Tree Tsunami program after his party won the July 2018 national election and he became prime minister.

Third-party audit

Last week, the Pakistani government signed an agreement with a consortium of three international organizations for a third-party monitoring and evaluation of the “Ten Billion Tree Tsunami” program from 2020 to 2024.

The consortium comprises WWF-P, the U.N. Food and Agriculture Organization (FAO) and ICUN-P.

FAO deputy representative Farrukh Toirovi described the program as a historic undertaking by Pakistan.

“This is a project which will benefit not only today the people of Pakistan, but also it will be benefiting the people all around the world and the region, and also for the people of the generations to come,” Toirovi said. "We from FAO are interested in this project so that we can take these lessons from Pakistan and try to use it also in other countries.”

Hammad Khan Naqi, director general of the WWF-Pakistan, explained that his organization will evaluate 30% of the plantation sites, 30% for wildlife conservation and 100% percent of the protected areas across the country.

Pakistani officials say the unprecedented third-party monitoring of a government project will ensure impartial “verification, transparency and accountability” of the massive reforestation drive and of the public funds being spent on it.
Riaz Haq said…
Energy crisis have devastated Pakistan’s economy through the country’s energy sector offered investment opportunities of over $100 billion a government estimate said. This included about $45 billion in power generation, $20 billion in transmission and $15-20 billion in distribution

https://www.thenews.com.pk/print/739524-govt-set-to-expedite-foreign-funded-energy-projects

The NCC-FFP reviewed progress of the development projects of power sector funded by ADB (Asian Development Bank), WB World Bank), IsDB (Islamic Development Bank), Japan, France, Germany and the USA” a statement said.

At present, 14 foreign-funded projects including power generation, transmission and distribution amounting to $3.418 billion are under implementation. “The purpose of high-level meeting was to track physical and financial progress and identify issues and bottlenecks hampering smooth implementation of foreign-funded projects in power sector,” the statement quoted Bakhtyar as saying. Bakhtyar said the government is focusing on energy sector reforms and energy efficiency through development of renewable and clean energy at affordable prices, reliable transmission system and improved distribution network.

Energy crisis have devastated Pakistan’s economy through the country’s energy sector offered investment opportunities of over $100 billion a government estimate said. This included about $45 billion in power generation, $20 billion in transmission and $15-20 billion in distribution

Energy minister Khan directed the line departments of power division to fast track implementation of the projects and prompt redressal of issues for expeditious execution of projects in energy sector. “He especially emphasized on the major problematic projects including Jamshoro Power Generation Project, Advance Metering Infrastructure and CASA 1000 & Other Transmission Lines and set the timelines to resolve the bottlenecks.”

Both ministers agreed to hold follow-up meeting of National Coordination Committee on Energy sector in next month.

Earlier, Prime Minister Imran Khan constituted the high-level “National Coordination Committee on Foreign-Funded Projects” in order to fast track the disbursement & implementation of external economic assistance.

Ministry of economic affairs was assigned to convene the meetings of this committee and submit a progress report to Prime Minister on monthly basis. Minister Bakhtyar would be chairperson of the committee. Deputy chairman, Planning Commission, secretary EAD, representatives of PM’s Office, finance division and provincial P&D departments and boards of revenues also attended the meeting.

Riaz Haq said…
First Hualong One #nuclear reactor achieves criticality in #China. 2 HPR1000 units, each 1100MW, are under construction at #Pakistan's #Karachi nuclear power plant.began. They are planned to enter commercial operation in 2021 and 2022.- World Nuclear News


https://www.world-nuclear-news.org/Articles/First-Hualong-One-reactor-achieves-criticality

China's Ministry of Ecology and Environment issued the operating licence for Fuqing 5 on 4 September. The process of loading the 177 fuel assemblies into the reactor core began the same day and was completed on 10 September. Yesterday, at 3.09pm, the reactor achieved first criticality after the boron concentration in the primary loop was diluted and the control rods were withdrawn.

Various commissioning tests will now be carried out at the Hualong One, prior to it being connected to the electricity grid. It will then undergo tests at increasing power output levels before entering a full-power demonstration operating assessment. During this assessment stage, the performance indicators of the unit will need to meet design standards and the relevant requirements of the power grid, which will indicate that the unit has achieved formal commercial operating conditions.

China's State Council gave final approval for construction of Fuqing units 5 and 6 in April 2015. The pouring of first concrete for Fuqing 5 began in May that year, marking the official start of construction of the unit. Construction of unit 6 began in December the same year. The inner dome of unit 5 was installed on the containment building in May 2017, with the outer dome installed in January 2018.


Hot testing at Fuqing 5 was completed on 2 March. These tests involved increasing the temperature of the reactor coolant system and carrying out comprehensive tests to ensure that coolant circuits and safety systems are operating as they should. Such testing simulates the thermal working conditions of the power plant and verifies that nuclear island and conventional equipment and systems meet design requirements.

Construction of two demonstration Hualong One (HPR1000) units is also under way at China General Nuclear's Fangchenggang plant in the Guangxi Autonomous Region. Those units are expected to start up in 2022. CNNC has also started construction of two Hualong units at the Zhangzhou plant in Fujian province, plus the first of two units at Taipingling in Guangdong.

Two HPR1000 units are under construction at Pakistan's Karachi nuclear power plant. Construction began on Karachi unit 2 in 2015 and unit 3 in 2016; the units are planned to enter commercial operation in 2021 and 2022.
Riaz Haq said…
Pakistan’s Peaceful Uses Of Nuclear Energy – OpEd
November 27, 2020
By Sher Bano

https://www.eurasiareview.com/27112020-pakistans-peaceful-uses-of-nuclear-energy-oped/


Pakistan Atomic Energy Commission (PAEC), established in 1956 is the pioneer government agency to oversee the peaceful uses of nuclear technology in the country. It was established to contribute to Pakistan’s overall economic development through the utilization of nuclear energy in various public fields. These include; medical diagnosis/therapy, agricultural production, nuclear energy for power generation, and some other functions that involve peaceful uses of nuclear technology. In the early ’70s, PAEC constructed the first-ever 135 Megawatts (MWs) nuclear power plant at Karachi KANUPP. This was also the first-ever nuclear power generation plant in the developing or underdeveloped world. The successful launch of this power plant later led to the development of four more nuclear plants at Chashma, the CHASNUPP-1, CHASNUPP-2, CHASHNUPP-3, and CHASHNUPP-4. Furthermore, Pakistan also intends to build two nuclear power plants known as K-2 and K-3 at Karachi, one at Chashma, and two at Muzaffargarh. This is part of Pakistan’s long-term plan to produce 40,000 Megawatts MWs of electricity by using nuclear energy by the year 2050. Here it is quite noteworthy to specify that nuclear power generation is believed to be one of the economical and reliable sources of electricity generation. Such credentials have included Pakistan among the list of 30 countries that have fully operational nuclear plants. Along with this, Pakistan is also among the only ten countries in the world that have completed the nuclear fuel cycle.

Likewise, in the field of agriculture, nuclear technology has contributed to various landmark achievements for Pakistan. In this regard, the PAEC has developed multiple facilities for the advancements in the field of agriculture and food in collaboration with the IAEA. It has also launched various programs to increase the nutritional value of staple foods so that it can meet the United Nations Sustainable Development Goals (SDGs) to eliminate malnutrition and hunger. Furthermore, various irradiation techniques have been used in the agriculture sector to enhance the quality of food and to extend the shelf life of products at the farms. Also, PAEC is working on various food fortification initiatives to enhance the vitamin and mineral content in the food and to eradicate malnutrition. This is further evident from the fact that nearly 98 new high-yielding and stress-tolerant crops have been created by using nuclear technology. For the availability of clean water in the country, PAEC for years has been collaborating with IAEA to analyze and detect pollutants in water by using isotopic and nuclear techniques. Pakistan has also built laboratories by collaborating with IAEA for mass breeding of insects that fight pests attacking the crops and thus the use of pesticides is decreased.

In Pakistan, nuclear technology has significant use in the field of medical science especially for the diagnosis and treatment of cancer disease. In this regard, over the years, 18 cancer treatment centers have been developed by PAEC where nearly 0.7 million cancer patients have been treated to date. This counts for almost 80% of the total cancer patients from all over the country. Radiation and various other nuclear techniques are used for treating cancer. Likewise, various cancer awareness campaigns are being run by the PAEC so that cancer gets diagnosed at the early stages. Other than these, PAEC has been collaborating with international organizations like the WHO, IRC, IAEA, and UICC, etc. This has facilitated the access of Pakistani scientists and doctors to the relevant international institutions and provides opportunities for training in the field of nuclear medicines. Taking part in various seminars and workshops also keeps the nuclear medical professionals updated about the latest developments in this field.
Riaz Haq said…
Fuel loading starts for 1,100 MW K-2 #nuclear power plant in #Karachi. The other plant, 1,100 MW K-3, is expected to become operational by the end of 2021. Both have remained on schedule despite disruption from #COVID19 pandemic. #Pakistan #China #CPEC https://www.dawn.com/news/1593541

A spokesperson for the Pakistan Atomic Energy Commission (PAEC) said fuel loading for the newly built Karachi Nuclear Power Plant Unit-2 (K-2) was started on Tuesday after obtaining fuel load permit from the Pakistan Nuclear Regulatory Authority.

K-2 is a pressurised water reactor based on the Chinese HPR-1000 technology and a third generation plant equipped with advanced safety features, according to the spokesperson. The construction of K-2 plant started on Aug 31, 2015 and its commercial operation will begin in April 2021 after undergoing several operational and safety tests.

Agreements signed with Chinese firm for construction of hydropower project in Azad Kashmir

K-2 is one of the two 1,100MW nuclear power plants being constructed at Karachi. The other plant, K-3, is expected to become operational by the end of 2021. The completion of these nuclear power plants has remained largely on schedule despite the difficult times due to Covid-19 pandemic. The fuel loading was witnessed by Director General of the Strategic Plan Division Lt Gen Nadeem Zaki Manj, PAEC Chairman Mohammad Naeem and senior Chinese and Pakistani officials.

Separately, the AJK government and Chinese firm China Gezhouba Group and its local partner Laraib Group signed implementation agreement and water use charges agreement for construction of Azad Pattan Hydropower Project as part of the China-Pakistan Economic Corridor (CPEC).

With an investment of over $1.35 billion, the 700.7MW project would involve no fuel import and enable the country to move towards cheaper and greener power generation, said AJK Prime Minister Raja Farooq Haider Khan on the occasion.

Federal Minister for Power Omer Ayub Khan, Minister for Planning Asad Umar, Chairman of defunct-CPEC Authority retd Lt Gen Asim Saleem Bajwa, AJK Chief Secretary Dr Shahzad Khan Bangash and Managing Director of Private Power and Infrastructure Board (PPIB) Shah Jahan Mirza attended the agreement signing ceremony.

The project agreements — GoAJ&K Implementation Agreement and GoAJ&K Water Use Agreement — were signed by Zafar Mahmood Khan, electricity secretary of AJK, and Li Xiaotao, CEO of Azad Pattan Power Private Limited.

The Government of Pakistan Implemen­tation Agreement, Government of Punjab Water Use Agreement and Tripartite Power Purchase Agreements of the project had already been signed in the presence of Prime Minister Imran Khan in July this year. Tuesday’s agreement signing will enable the achievement of financial close of the project.

The letter of support (LOS) for the project was issued by the PPIB to Azad Pattan Power Project Limited. It is a run-off-the river scheme on River Jhelum located at the dual boundary between AJK (Bagh district) and Punjab (Rawalpindi district).

China Gezhouba Group and Laraib Group Pakistan are the shareholders of the project. The consortium of lenders consists of China Development Bank, China Construction Bank, Industrial and Commercial Bank of China and Bank of China.

Azad Pattan Project is being implemented by the PPIB under the Policy for Power Generation Projects 2002 on built, own, operate and transfer basis for a term of 30 years after which it will be transferred to the AJK government free of cost. The project is expected to provide about 3,266 GWh electricity per year to the national grid by 2027.

The project would a play crucial role in stimulating local economy by providing employment and business opportunities during its construction periods, said the ministry of power. The governments of AJK and Punjab would earn significant amount of revenue on account of taxes, fees, etc.
Riaz Haq said…
Going carbon free
By Engr. Hussain Ahmad Siddiqui Mon, 12, 20

https://www.thenews.com.pk/magazine/money-matters/754611-going-carbon-free


Now known as Chashma Nuclear Power Plant-1 (or CHASNUPP-1 or C-1), it has PWR (pressurised water reactor) type reactor of 325MWe gross or 300MWe net capacity. Since then, there has been a series of nuclear power plants constructed at Chashma site with the generous help of China. These are CHASNUPP-2 (or C-2) of 325MWe gross or 300MWe net capacity, grid-connected in 2011, CHASNUPP-3 (or C-3) of 340MWe gross or 315MWe net capacity, grid-connected in 2016, and CHASNUPP-4 (C-4) of 340MWe or 313MWe net capacity, which was grid connected in 2017.

Today, cumulative capacity of these nuclear power plants is 1,467MWe gross or 1,318MWe net, generating 9,705GWh (Gigawatt-hours) with a share of over seven percent in power generation mix of total 134,745GWh generated during last fiscal year ending June 30, 2020. Overall capacity factor of these nuclear power plants is at par with global levels. All these nuclear power plants are operating under international safeguards of the International Atomic Energy Agency (IAEA), Pakistan being an IAEA Member State since 1957.

In January 2018, the IAEA launched a four-year technical cooperation project titled “Strengthening and Enhancing Capabilities of Pakistan’s National Institutions to Support a Safe, Reliable and Sustainable Nuclear Power Programme”. Subsequently, Pakistan signed in September 2019 the fourth “IAEA Country Programme Framework for 2020-2025”, which is a medium-term plan of technical cooperation for transfer of nuclear technology. Based on this document, the IAEA technical cooperation resources will be directed to support national development goals in the areas of, inter alia, nuclear power development and nuclear safety and security.

Currently, there are two nuclear power plants under construction at Karachi—KANUPP-2 (K-2) and KANUPP-3 (K-3), each of 1,145MWe capacity. These are Chinese third-generation Hualong One (also known as HPR 1000) reactors based on PWR technology. The first nuclear power plant based on Hualong One technology has been tested and grid-connected in China ten days ago, on November 27. The power plant located in Fuqing city in Fujian province meets the strictest safety standards in the world and meets designed requirements for technical performance, China claims.

Construction of K-2 and K-3 started in August 2015 and May 2016, respectively. K-2 is in advanced stage of construction. Cold testing of K-2 was completed in December 2019. Concreting of outer dome of the double-layer containment of K-3 was completed in April 2020. Thus, K-2 is scheduled for commercial operations by the end of 2021, whereas K-3 is expected to complete in 2022. The Chinese have committed to supply reactors fuel (uranium) for design lifetime of sixty years of these plants. The two projects are covered under the China-Pakistan Economic Corridor (CPEC) programme. The IAEA applies safeguards to K-2 and K-3 as well under the agreement concluded in May 2017. With the completion of K-2 and K-3 total installed capacity of nuclear power generation would be 3,757MWe.

To meet energy needs for socio-economic development, Pakistan plans to enhance nuclear-based power generation to 8,800MWe total installed capacity by 2030 targeting 25 percent share in overall power generation mix by then. It is decided that China’s Hualong One unit of 1,145MWe capacity, as installed at K-2 and K-3, will be replicated for future projects. In November 2017, Pakistan signed Cooperation Agreement with the Chinese on the construction of CHASNUPP-5 as a Hualong One unit. It is planned to construct another unit at Muzaffargarh, near Taunsa-Punjnad Canal, while four other sites have been identified, in consultation with the IAEA, for the remaining projects planned for completion by 2030.
Riaz Haq said…
First Hualong One reactor achieves initial criticality


https://www.ans.org/news/article-2322/first-hualong-one-reactor-achieves-initial-criticality/

Also known as the HPR1000, the Hualong One is a Chinese-designed, 1,000-MWe Generation III pressurized water reactor. Fuqing-5’s twin HPR1000, Fuqing-6, is scheduled to start contributing power to the grid next year.

Located in China’s Fujian Province, Fuqing also houses four 1,000-MWe CPR-1000 PWRs, with commercial start dates of November 2014, October 2015, October 2016, and September 2017.

On the horizon: In addition to the new units at Fuqing, CNNC is building two Hualong One reactors at the Zhangzhou site in Fujian Province (construction of Unit 1 began in October 2019, while Unit 2’s construction commenced just recently) and one at Taipingling in Guangdong Province, with another planned for the site.

Also, China General Nuclear is building two Hualong One reactors (Units 3 and 4) at its Fangchenggang plant in Guangxi Province.


Riaz Haq said…
Pakistan emerging as ‘global leader in tackling climate change’ | Pakistan – Gulf News

https://gulfnews.com/world/asia/pakistan/pakistan-emerging-as-global-leader-in-tackling-climate-change-1.76780340


The British government has commended Pakistan’s ambitious 10 billion tree plantation project, describing it as one of the most successful green initiatives that the rest of the world can learn from and implement to tackle climate change.

“Pakistan’s 10 billion tree tsunami project is one of the most ambitious tree planting initiatives in the world and is a successful precedent for others to follow,” said UK Environment Minister, Lord Goldsmith of Richmond Park. “I absolutely, enthusiastically, commend and celebrate Pakistan’s 10 billion tree tsunami initiative and the tens of thousands of jobs that have been created due to the project. It goes to show what is possible and what can be achieved,” said the UK minister.


Riaz Haq said…
#Pakistan: #KP provincial government signs pact with #Chinese company for 300MW, Rs. 85 billion #Balakot #hydropower project. #ADB to provide bulk of financing. #renewableenergy #ClimateAction #PTI https://www.dawn.com/news/1611678

PESHAWAR: The Khyber Pakhtunkhwa government on Tuesday signed an agreement with a Chinese company for the construction of the 300-megawatt Balakot hydropower project.

The 300MW project — said to be the biggest-ever power generation plant in the province — would be constructed with an estimated cost of Rs85 billion in a period of six years with the financial assistance of the Asian Development Bank, said an official statement.

At the signing ceremony, Khyber Pakhtunkhwa Chief Minister Mahmood Khan was the chief guest. Officials of the Pakhtunkhwa Energy Develop­ment Organisation (PEDO) and China Gezhouba Group signed the agreement. KP Finance Minister Taimur Saleem Jhagra and Adviser to CM KP Himayatullah Khan also attended the event along with the high-ups of the energy and power department.

Speaking on the occasion, CM Khan termed the project as of vital importance for the province and a milestone achievement of the provincial government. He said the groundbreaking of the mega-project was expected to be performed by mid-April by Prime Minister Imran Khan.


Rs85bn project will be constructed in six years

The project would play an important role in boosting industrial activities, job creation and overall development of the province, he said, adding that during the construction phase, the project would generate around 4,000 job opportunities. Upon completion, it is expected to generate revenue of Rs14bn per annum, he added.

The CM maintained that power generated by Balakot hydropower project would be provided to local industries as well as to domestic consumers at relatively cheap rates.

The incumbent provincial government was taking result-oriented steps under a well-devised strategy to ensure optimum utilisation of the hydropower potential of the province with the aim to meet its energy requirements and strengthen its economy, the chief minister said.

So far various hydropower projects with a total capacity of 160MW have been completed under PEDO, whereas work is in progress on various other projects having a total capacity of 216MW.

Published in Dawn, March 10th, 2021
Riaz Haq said…
Why Covering Canals With Solar Panels Is a Power Move
Covering waterways would, in a sense, make solar panels water-cooled, boosting their efficiency.

https://www.wired.com/story/why-covering-canals-with-solar-panels-is-a-power-move/


Scientists in California just ran the numbers on what would happen if their state slapped solar panels on 4,000 miles of its canals, including the major California Aqueduct, and the results point to a potentially beautiful partnership. Their feasibility study, published in the journal Nature Sustainability, finds that if applied statewide, the panels would save 63 billion gallons of water from evaporating each year. At the same time, solar panels across California’s exposed canals would provide 13 gigawatts of renewable power annually, about half of the new capacity the state needs to meet its decarbonization goals by the year 2030.

California’s water conveyance system is the world’s largest, serving 35 million people and 5.7 million acres of farmland. Seventy-five percent of available water is in the northern third of the state, while the bottom two-thirds of the state accounts for 80 percent of urban and agricultural demand. Shuttling all that water around requires pumps to make it flow uphill; accordingly, the water system is the state’s largest single consumer of electricity.

---------------------

Govt plans to install floating solar panels on dams
They will help reduce evaporation of water, generate clean electricity

https://tribune.com.pk/story/2110629/2-govt-plans-install-floating-solar-panels-dams

He (Minister Omar Ayub) announced that the government was planning to install floating solar panels on the country’s big water reservoirs and along canals in a bid to generate thousands of megawatts of clean energy.

This is part of the government’s plan to give priority to an increase in the share of renewable energy in the total energy mix.

He revealed that floating solar panels would be installed on Tarbela, Mangla, Ghazi Barotha and Khanpur reservoirs besides canals. “It will not only help to reduce evaporation of water but will also generate electricity,” the minister emphasised.

Speaking at a conference on “Water Crisis: An Imminent Danger to Pakistan’s Stability”, Khan warned India that Pakistan would swiftly retaliate if New Delhi violated the Indus Waters Treaty.

“If India tries to make the Indus Waters Treaty as a weapon, then answer from Pakistan will be swift as we will defend our sovereignty.”

He urged the international community to take notice of Indian atrocities in the occupied valley of Kashmir.

He was of the view that if proper investment was made in the water sector, especially in water storages, then it had the potential to take up the country’s gross domestic product (GDP) growth by one percentage point.

Despite its importance in economic growth, the minister decried, no work was carried out for the construction of dams after Tarbela and Mangla and no big dam was commissioned after 1960.

“Our government is actively working on a plan to harness the water resources in order to add 18,000-20,000 megawatts of hydroelectric power to the system,” he said. The minister pointed out that the current installed power generation capacity from all sources stood at 31,000MW, which would be enhanced to 55,000MW by 2030.

By the year 2025, around 8,000MW of renewable energy would be added to the system and 20,000MW would be added by 2030, he anticipated.

Riaz Haq said…
Nuclear power plants produce no greenhouse gas emissions during operation, and over the course of its life-cycle, nuclear produces about the same amount of carbon dioxide-equivalent emissions per unit of electricity as wind, and one-third of the emissions per unit of electricity when compared with solar.

https://www.world-nuclear.org/nuclear-essentials/how-can-nuclear-combat-climate-change.aspx

Experts have concluded that in order to achieve the deep decarbonisation required to keep the average rise in global temperatures to below 1.5°C, combating climate change would be much harder, without an increased role for nuclear. Because nuclear power is reliable and can be deployed on a large scale, it can directly replace fossil fuel plant, avoiding the combustion of fossil fuels for electricity generation. The use of nuclear energy today avoids emissions roughly equivalent to removing one-third of all cars from the world’s roads.

Modern society is becoming more and more dependent on electricity, with demand steadily increasing as transport, domestic heating and industrial processes are increasingly electrified. Whilst electricity is clean at the point of use, its generation currently produces over 40% of all energy-related carbon emissions. Decarbonising the electricity supply, whilst providing affordable and reliable electricity to a growing global population, must be central to any climate change strategy.Nuclear energy has shown that it has the potential to be the catalyst for delivering sustainable energy transitions, long before climate change was on the agenda. France generates over 70% of its electricity from nuclear power – the largest nuclear share of any country globally – and its electricity sector emissions are one-sixth of the European average. In around 15 years, nuclear power went from playing a minor role in the French electricity system to producing the majority of its electricity, showing that nuclear energy can be expanded at the speed required to effectively combat climate change.
Riaz Haq said…
Apparently irked over not being invited by longtime ally US to an upcoming meeting on the climate change crisis, Pakistan on Saturday said its commitment to addressing the simmering issue is “well accepted and appreciated around the world.”

https://www.aa.com.tr/en/asia-pacific/pakistan-responds-to-us-climate-summit-snub/2190225


US President Joe Biden has invited 40 world leaders to a two-day Leaders Summit on Climate “to galvanize efforts by the major economies to tackle the climate crisis,” the White House announced on Friday.

The virtual summit, which follows Washington’s return to the 2016 Paris agreement, is slated to be held on April 22 and April 23.

Responding to the US snub, Foreign Ministry spokesperson Zahid Hafeez Chaudhri issued a statement outlining Islamabad’s contributions to the global fight against climate change.

“Pakistan’s landmark initiatives like the Billion Tree Tsunami have won international acclaim, including from the World Economic Forum,” he said, referring to a nationwide tree plantation drive spearheaded by Prime Minister Imran Khan’s government.

“Pakistan is also meaningfully contributing to shape the global climate change discourse, inter alia, as the Vice President of the UN Framework Convention on Climate Change and member of the Intergovernmental Panel on Climate Change,” read the statement.

“Pakistan also co-chaired the multibillion-dollar Green Climate Fund, established to support climate actions in developing countries, last year.”

The summit, Chaudhri pointed out, would bring together “leaders from countries responsible for approximately 80 percent of global emissions and GDP.”

“Pakistan, despite being among the top ten countries affected by climate change, is one of the lowest emitters – with less than one percent of the global emissions,” he said.

“Climate change is one of the defining challenges of our times that can only be countered through inclusive, cooperative and forward-looking policies. Pakistan remains fully committed to play its due role in this fight.”
Riaz Haq said…
#Karachi's 1,100 MW #nuclear power plant unit 2 inaugurated by #Pakistan PM. #ImranKhan said #environmental and #economic benefits from it will be "huge" in a country that is particularly vulnerable to #climatechange. #ClimateCrisis https://world-nuclear-news.org/Articles/Karachi-unit-2-inaugurated-by-Pakistan-PM


Karachi 2 joins the five nuclear power plants already operating under the management of the Pakistan Atomic Energy Commission.

Speaking from Islamabad by videolink in a ceremony that also marked the 70th anniversary of the establishment of diplomatic relations between Pakistan and China, Khan said the plant's 1100 MW of clean energy would "almost double" Pakistan's nuclear power generation.

Karachi unit 3 - which like unit 2 is also an 1100 MW Hualong One unit supplied by China National Nuclear Corporation (CNNC) - is expected to generate electricity early next year, he said. The Karachi units are the first exports of the Hualong One, which is promoted on the international market as HPR1000.

"It is worth mentioning here that clean, reliable and affordable power generation will also bring economic benefits to the country," Khan said.

Construction of Karachi 2 began in 2015 and the unit achieved first criticality in February and was connected to the grid in March after the completion of commissioning tests. The plant's operational period is 60 years, which can be extended for another 20 years.

According to the Associated Press of Pakistan, China Atomic Energy Authority Chairman Zhang KeJian said the launch of Karachi 2 showed the commitment of both countries to the peaceful use of nuclear energy for the socioeconomic benefit of their people. CNNC Chairman China Yu Jian Feng said technology transfer and nuclear cooperation between China and Pakistan would "achieve new heights".
Riaz Haq said…
Pakistan Nears Debt-for-Nature Swap Agreement With Creditors
By Greg Ritchie and Faseeh Mangi
May 24, 2021, 2:58 AM PDT Updated on May 24, 2021, 6:24 AM PDT

https://www.bloomberg.com/news/articles/2021-05-24/pakistan-nears-debt-for-nature-swap-agreement-with-creditors

Pakistan is closing in on a deal with bilateral creditors that would tie debt relief to the achievement of biodiversity goals, government officials said.

The South Asian nation is working with lender countries on a debt-for-nature swap program, which would see debt relief in return for binding commitments to achieve conservation targets. An official letter of intent could be announced as soon as World Environment Day on June 5, which Pakistan is hosting this year.

“Four to five creditors will commit to an intent to engage for a debt-for-nature swap,” Malik Amin Aslam, climate change adviser to Prime Minister Imran Khan, said in an interview.


The country is working with the U.K., Germany, Italy and Canada, though that’s yet to be finalized, according to Noor Ahmed, secretary at the government’s economic affairs division. Apart from Germany, those aren’t among Pakistan’s largest outstanding bilateral creditors, with that list topped by China, Japan and the United Arab Emirates, according to an International Monetary Fund report released last month.


Debt swaps have been around for decades, with the United Nations putting the value of debt-for-climate and nature agreements at over $2.6 billion from 1985 to 2015 -- though most of that was during the 1990s. There’s been a push to repopularize the structure as part of a broader campaign to realign finance with the protection of the natural world at the same time as reducing nations’ debt strain after the coronavirus pandemic.

Earlier this year, Pakistan said it was developing a so-called nature-performance bond, a new instrument that would tie the cost of repayments to quantified biodiversity targets. That’s part of a plethora of recently-created debt types aimed at tapping surging investor interest in environmental, social and governance assets.


Riaz Haq said…
Siemens Gamesa books 410 MW of turbine orders in Pakistan in FY 2019/2020


https://renewablesnow.com/news/siemens-gamesa-books-410-mw-of-turbine-orders-in-pakistan-in-fy-20192020-715727/


Gamesa Renewable Energy SA (BME:SGRE) has received 410 MW worth of wind turbine orders from Pakistan during its fiscal year to end-September.

Of the total, orders for 260 MW were booked in the final quarter of the 2019/2020 fiscal year, the turbine maker said.

The machines will be distributed between eight wind farm projects. Two of the projects are already under construction, with commissioning set to take place in November 2020 and February 2021.

The eight projects represent 205 of turbines from the 2.X platform, which Siemens Gamesa will supply, install and commission in partnership with an engineering, procurement and construction (EPC) contractor.

By the end of 2021, all eight wind farms will be fully operational. Once online, they will be capable of covering power consumption needs of up to 600,000 local households each year.

According to Siemens Gamesa, 40 million of people in Pakistan have no access to electricity. The government is committed to bring in modern renewables into the power mix, currently dominated by imported oil and natural gas.
Riaz Haq said…
Night view of a well-lit grid-station in #Lahore. It connects #Punjab to 878 Km 600 Kv HVDC $2.1 billion Lahore-#Matiari (#Sindh) #power #transmission line that recently became part of #Pakistan's national grid. #CPEC #China

https://twitter.com/haqsmusings/status/1427433907608199175?s=20
Riaz Haq said…
Fuel being loaded into #Pakistan's 1,100 MW #nuclear power plant K-3 in #Karachi to start generating #electricity by March 2022, brining nuclear to 10% of power in the country. Earlier, K-2 successfully started commercial operation on May 21, 2021. #energy https://www.devdiscourse.com/article/headlines/1867657-pakistan-loads-fuel-in-chinese-assisted-karachi-nuclear-power-plant-unit-3

akistan has completed the loading of fuel at its Chinese-assisted Karachi Nuclear Power Plant Unit-3 to celebrate three decades of cooperation with its “all-weather ally” China, according to a media report here on Saturday.

Pakistani authorities, after getting a formal permit from the Pakistan Nuclear Regulatory Authority (PNRA), completed the fuel loading process of the second 1,100-megawatt nuclear power plant on Friday, the state-run Associated Press of Pakistan (APP) reported.

It said that the ceremony to mark “three decades of cooperation between China and Pakistan in the field of peaceful use of nuclear energy” as well as of the fuel loading of Karachi Nuclear Power Plant Unit-3, commonly known as K-3, was attended by top officials of nuclear energy related organisations from the two countries.

The report said that K-3 is in the final stages of commissioning and after operational and safety tests, the plant is expected to begin commercial operation by the end of March 2022.

A new era in the nuclear power development programme of Pakistan commenced with the signing of the 'Agreement for Cooperation in Peaceful Uses of Nuclear Energy' between the governments of China and Pakistan in 1986, according to the report.

However, the first concrete step in the remarkable journey was taken 30 years ago when China National Nuclear Corporation (CNNC) and Pakistan Atomic Energy Commission (PAEC) signed the contract for construction and installation of a 325-megawatt Pressurised Water Reactor (PWR) at Chashma on December 31, 1991, it said.

The cooperation strengthened with the construction of three more nuclear power plants at Chashma Nuclear Power Generation Station (CNPGS) site.

The contract for the construction of two more units having a generation capacity of 1,100 megawatts each near Karachi was signed on February 18, 2013. These units are called Karachi Nuclear Power Plant Unit-2 and 3 (K-2 and K-3).

After the groundbreaking of K-2 and K-3 in November 2013, the construction of K-3 was formally started.

Despite the COVID-19 pandemic, both Pakistan and China faced all odds and continued the construction work. K-2 successfully started commercial operation on May 21, 2021, and now K-3 is expected to do so by the end of March 2022.

K-2 and K-3 are pressurised water reactors based on the Chinese ACP-1000 design and are generation-three plants equipped with advanced safety features.

With the connection of K-2 and K-3 into the national grid, the share of nuclear power in the energy mix of Pakistan will exceed 10 per cent, according to the report.

(This story has not been edited by Devdiscourse staff and is auto-generated from a syndicated feed.)
Riaz Haq said…
Sohail Ahmed @sohailahmedsa🇵🇰 Alhumdulillah Karachi Nuclear Power Plant (KANUPP) Unit-3 (K-3) is now critical.
KNPP-2 & KNPP-3 are 1100 MW each

https://twitter.com/sohailahmedsa/status/1495974363069399042?s=20&t=5RWyuRFkBRfeFG_Djqk90Q
Riaz Haq said…
Pakistan power project using China’s Hualong One connected to grid - Global Times

https://www.globaltimes.cn/page/202203/1253974.shtml


The (1,100 MW) K-3 unit of the Karachi Nuclear Power Project in Pakistan, the fourth entity to use a China-designed third-generation nuclear reactor, was successfully connected to the grid on Friday, laying solid foundations for commercial operation.

All four of the units adopting China’s Hualong One nuclear reactor are now connected to the grid and are generating electricity, China National Nuclear Corp (CNNC) said in a statement on Friday.

Each Hualong One unit is expected to generate nearly 10 billion kWh of electricity annually after being completed, which can meet the annual electricity demand of more than 4 million households in Pakistan – equivalent to reducing use of standard coal by 3.12 million tons, and reducing carbon dioxide emissions by 8.16 million tons every year. It is also the equivalent of planting more than 70 million trees, CNNC said.

It is of great significance for optimizing Pakistan's energy structure, as well as reaching carbon peak and carbon neutrality goals, CNNC added.

The success in construction and operation of the nuclear reactors in Pakistan will make the Hualong One technology better received in the global market, especially in countries and regions participating in the Belt and Road Initiative, observers said.

The K-2 unit of the Karachi Nuclear Power Plant in Pakistan, which also uses Hualong One, officially started commercial operation on May 20 last year.

As China's "calling card" for its nuclear power industry, Hualong One has become one of the most widely recognized third-generation nuclear power reactors in the market.

All of Hualong One’s core components are produced domestically, and it has a design life of 60 years and meets the strictest safety standards in the world, according to a report from the Xinhua News Agency.

In May 2015, construction began on the world's first Hualong One demonstration project in Fuqing. On January 30, the world's first nuclear power unit under Hualong One, unit 5 of CNNC's Fuqing nuclear power plant, entered commercial operation.

With Hualong One online, China is now at the world forefront of third-generation nuclear technology, alongside countries like the US, France and Russia, the Xinhua News Agency reported, citing CNNC Chairman Yu Jianfeng.

The commercial use of Hualong One will also help to meet China’s goal for CO2 emissions to peak before 2030 and to achieve carbon neutrality before 2060, Yu added.
Riaz Haq said…
Fitch Affirms Pakistan Water and Power Development Authority at 'B-'; Outlook Stable


https://www.fitchratings.com/research/international-public-finance/fitch-affirms-pakistan-water-power-development-authority-at-b-outlook-stable-14-03-2022



WAPDA is established under a special statute. The Authority has close operational and administrative linkage to the government and is mandated to develop water and power resources in Pakistan. The government exercise strong influence over WAPDA's corporate governance and debt, sanctioned by the government, shall be transferred to the government according to the Pakistan Water and Power Development Authority Act.

KEY RATING DRIVERS
Status, Ownership and Control: 'Very Strong'


Our 'Very Strong' assessment of 'Status, Ownership and Control' remains unchanged, given the strong statutory support, stable government ownership - which we do not expect to change - and high level of government control. Employees of WAPDA are deemed to be public servants when acting in pursuance of WAPDA activities. The government has strong influence on WAPDA's corporate governance, including budget, accounts, financing activity and new power station investment plans, because the Authority is mandated to execute the government's responsibility of utilising Pakistan's water and power resources.

Support Track Record: 'Very Strong'


The build-up of circular debt in the energy sector exposes WAPDA to external funding. The government aims to mitigate the circular debt issue by providing financial support; it had guaranteed 22% of WAPDA's interest-bearing debt as of June 2021 and 56% of the debt comprises of government loans. The government will be liable for loans passed by the Authority with the sanction of the government under the WAPDA Act. Supportive policies, such as corporate tax exemptions, land acquisitions and a tariff mechanism, also enhance WAPDA's operational stability.

Socio-Political Implications of Default: 'Strong'


Pakistan's policies aim to boost the hydropower generation mix and reduce reliance on fossils. WAPDA's hydropower generation accounted for 27% of the generation mix in 2021, while other renewable energy only accounted for 3%. The government aims for hydro power to contribute over 40% of Pakistan's energy demand by 2030, implying that the development of hydropower generation is of significant strategic importance to the country. We believe WAPDA's installed capacity would be difficult to substitute and that any transition process would lead to severe service disruption.

Financial Implications of Default: 'Very Strong'


We deem WAPDA as a proxy financing vehicle for the government in the energy sector. The Authority still relies on the government to fund its investments, although it is expanding its borrowing capacity, including via recent bond issues. We believe the government's borrowing ability would be significantly impaired if WAPDA come under financial stress due to the high level of funding it receives from international development finance institutions and its debt mix - 78% of interest-bearing debt comprised loans or was guaranteed by the government.

Derivation Summary

WAPDA's ratings reflect our assessment of government linkage and support incentive and results in a weighted score of 50, based on our Government-Related Entities Rating Criteria. We adopt a top-down approach and equalise WAPDA's rating with those of Pakistan (B-/Stable), regardless of WAPDA's Standalone Credit Profile.

Riaz Haq said…
Nuclear power generation
By Engr. Hussain Ahmad Siddiqui Mon, 03, 22
This month is marked with Pakistan achieving milestone of 3,635-MWe cumulative nuclear power generation capacity as the third nuclear power plant at Karachi is connected to the national grid for testing, and will shortly commence commercial operations.

https://www.thenews.com.pk/magazine/money-matters/941162-nuclear-power-generation

his month is marked with Pakistan achieving milestone of 3,635-MWe cumulative nuclear power generation capacity as the third nuclear power plant at Karachi is connected to the national grid for testing, and will shortly commence commercial operations.

Commonly known as Kanupp-3 or K-3, it is of 1,145-MWe generation installed capacity and 1,100-MWe net capacity, which had attained criticality last month, and was undergoing safety tests and procedures. Generation cost is about Rs 9.59 per KWh (levelised). The foreign exchange portion of the project, which is about 80 percent of total cost, has been financed through a loan from the China’ state-owned The Export-Import Bank of China.

With the addition of K-3 nuclear power plant, currently there are total seven nuclear power plants installed in the country, out of which six, of cumulative installed capacity of 3,635-MWe, are in operation. The first–ever nuclear power plant constructed in the country, Kanupp-1 (K-1), has been permanently shut down. With the commencement of commercial operations of K-3, the share of nuclear energy in overall generation mix from all resources at national level has significantly increased, to over 9.1 percent. This share, which was 1.1 percent in 1990, has gradually and steadily increased in later years to 7.1 percent in 2020, before achieving the present level.

These nuclear power plants, established with technical and economic support of China, are owned and operated by the Pakistan Atomic Energy Commission (PAEC), and regulated by the Pakistan Nuclear Regulatory Authority (PNRA) under the safeguards of the International Atomic Energy Agency (IAEA). These facilities are located only at two sites — Chashma (District Mianwali) and Karachi. There are four nuclear power plants, namely Chasnupp-1 (C-1) of 325-MWe installed capacity, and plants C-2, C-3 and C-4, each of 340-MWe capacity.

These four plants at Chashma were commissioned in the years 2000, 2011, 2016 and 2017, respectively, and their corresponding operating licenses are valid until December 2030, 2026, 2026 and 2027. Pakistan has an impeccable record of safety and security in operating these nuclear power plants, as it follows best practices and standards set by the IAEA. Pakistan is currently ranked 17th out of 25 countries on Nuclear Materials Safety Index in terms of safety, and security and is placed above India.

Karachi Coastal Power Complex consists of two units of 1,145-MWe each installed capacity, known as K-2 and K-3 for which China has provided $6.5 billion loan on soft terms. The earlier unit K-2 was connected to the system of the National Transmission and Despatch Co (NTDC) in May 2021. These are third-generation nuclear power plants developed and tested by the Chinese as “Advanced China Pressurized ACP-1000”. Electricity transmission infrastructure for evacuation of power from these plants include additional 550kv and 220kv transmission lines of 16-km that have recently been completed by the NTDC at a cost of Rs5.6 billion.

The K-1nuclear power plant of 137-MWe capacity was constructed near Karachi in 1971, and connected to the national grid in October 1972. It was designed to operate for 30-years’operation. On end of its service life in 2002, the major balancing, modernization & rehabilitation (BMR) and safety upgrades of the facility were carried out by the PAEC, and it operated safely since 2003 till recently at de-rated capacity of around 98-MWe. After 50-years’ record successful operation the plant has been shut-down in August 2021 for dismantling and decommissioning.


Riaz Haq said…
Shehbaz Sharif, the newly installed prime minister of Pakistan, has ordered the completion of the $2.8bn Diamer Bhasha Dam in Kashmir three years earlier than scheduled.

https://www.globalconstructionreview.com/new-pakistan-pm-calls-for-completion-of-2-8bn-dam-three-years-early/

An element of the China-Pakistan Economic Corridor (CPEC), the dam is being built by a joint venture between China Power and the Frontier Works Organisation, an engineering arm of Pakistan’s army.

When work began in 2020, it was expected to finish in 2028. Sharif now wants this to happen in 2026.

He made the call during a speech delivered to the Water and Power Development Authority (WAPDA) at the site of the project on Sunday, newspaper Dawn reports.

He said the electricity and irrigation produced by the dam would help to make Pakistan “prosperous and progressive”.

Claiming to understand the difficult terrain of the area and Pakistan’s difficulties in raising funds for construction, he added: “I am sure that all of you are going to work as a team and make efforts for the biggest energy project and complete it as early as possible.”

He also urged international investors to come forward and invest in the project.

The project is to build a roller-compacted gravity dam with a barrier some 272m high, making it the tallest of its type in the world.

The reservoir will contain 10 cubic kilometres of River Indus water, and its two powerhouses are expected to generate 4.5GW of electricity, equivalent to 12% of Pakistan’s total installed capacity.

The dam is being built in mountainous terrain between Kohistan district in Khyber Pakhtunkhwa and Diamer district in Gilgit Baltistan.

According to Dawn, engineers who have completed hydropower projects in the region suggested that it was more likely that the project would take longer than nine years to complete, rather than fewer.

However, the Lahore Chamber of Commerce & Industry welcomed the expedited schedule.

Its president Mian Nauman Kabir said on Monday that the project would serve as a “lifeline” for the country by improving its energy mix, cutting its huge oil import bill and bringing down the cost of doing business.
Riaz Haq said…
Unit 3 of the Karachi nuclear power plant in Pakistan - a Chinese-supplied Hualong One reactor - reached 100% capacity for the first time on 31 March. The 1100 MWe pressurised water reactor is currently undergoing power ascension testing prior to entering commercial operation.

https://www.world-nuclear-news.org/Articles/Worlds-fourth-Hualong-One-unit-attains-full-power

Construction of Karachi 3, the second of two Hualong One units to be built near Paradise Point in the province of Sindh, began in May 2016. Hot functional testing of Karachi 3 - which simulate the temperatures and pressures that the reactor systems will be subjected to during normal operation and are carried out before loading nuclear fuel - was completed ahead of schedule on 4 November last year. It achieved first criticality on 21 February and was connected to the grid on 4 March.

Various performance and commissioning tests have since been carried out at power levels of 25%, 30%, 50%, 75% and 87% capacity, China National Nuclear Corporation (CNNC) said.

Once testing at full capacity is completed, Karachi 3 will perform a 100-hour demonstration run, after which it will enter commercial operation.

Karachi 2 entered commercial operation in May last year. The units are the first exports of CNNC's Hualong One, which is also promoted on the international market as HPR1000.

The Karachi site - also sometimes referred to as KANUPP - was home to Pakistan's first nuclear power reactor, Karachi 1 - a small 100 MWe (90 MWe net) Canadian pressurised heavy water reactor which shut down in 2021 after 50 years of operation.

The first domestic demonstration plants of CNNC's Hualong One design are Fuqing 5 and 6, in China's Fujian province. The units entered commercial operation in January 2021 and March this year, respectively.

Nuclear energy currently provides around 8% of Pakistan's energy mix from five reactors: four CNNC-supplied CNP-300 pressurised water reactors at Chashma in Punjab, and Karachi 2. CNNC in 2017 signed a cooperation agreement with the Pakistan Atomic Energy Commission on the construction of a Hualong One as a fifth unit at Chashma.

In February, Nucleoeléctrica Argentina and CNNC signed an engineering, procurement and construction contract for the development of the Atucha 3 nuclear power plant. The plant, to be sited near Lima, about 100 kilometres north west of Argentina's capital, Buenos Aires, will use the Hualong One technology.

Riaz Haq said…
New hydel projects to produce over 11,000MW
Will enhance overall hydroelectric power capacity to 20,684MW

https://tribune.com.pk/story/2382074/new-hydel-projects-to-produce-over-11000mw


ISLAMABAD:
The Water and Power Development Authority (Wapda) is pursuing six hydroelectric power projects that will add 11,241 megawatts of environment-friendly electricity to the existing hydel generation capacity of 9,443MW in the coming years.

Talking to APP, Wapda officials said that at present total installed capacity of 24 hydel power stations of Wapda stood at 9,443MW and the addition of 11,241MW would enhance it to 20,684MW.

The existing hydel power stations included Tarbela, Mangla, Ghazi Barotha, Neelum-Jhelum and Warsak, which contributed about 25% to the total system capacity of 36,166MW from all sources.

The net electricity output of those power stations was about 32,000 gigawatt-hours (GWh) per annum.

Sharing details of the upcoming hydel power projects, the officials said that the Dasu Hydropower Project would contribute 4,320MW, Tarbela 5th Extension 1,510MW, Mohmand Dam 800MW, Diamer-Bhasha Dam 4,500MW, Keyal Khwar Power Project 128MW and Kurram Tangi 83.4MW to the national grid system.

Meanwhile, Pakistan Atomic Energy Commission has developed several nuclear power projects to support economic uplift in Pakistan.

Total installed capacity of the nuclear power plants connected with the national grid was 3,530MW, which included 1,330MW Chashma nuclear power project and 2,200MW Karachi nuclear power project.
Riaz Haq said…
Scientists Achieve Nuclear Fusion Breakthrough With Blast of 192 Lasers
The advancement by Lawrence Livermore National Laboratory researchers will be built on to further develop fusion energy research.

https://www.nytimes.com/2022/12/13/science/nuclear-fusion-energy-breakthrough.html


If fusion can be deployed on a large scale, it would offer an energy source devoid of the pollution and greenhouse gases caused by the burning of fossil fuels and the dangerous long-lived radioactive waste created by current nuclear power plants, which use the splitting of uranium to produce energy.

Within the sun and stars, fusion continually combines hydrogen atoms into helium, producing sunlight and warmth that bathes the planets. In experimental reactors and laser labs on Earth, fusion lives up to its reputation as a very clean energy source.

There was always a nagging caveat, however. In all of the efforts by scientists to control the unruly power of fusion, their experiments consumed more energy than the fusion reactions generated.

That changed at 1:03 a.m. on Dec. 5 when 192 giant lasers at the laboratory’s National Ignition Facility blasted a small cylinder about the size of a pencil eraser that contained a frozen nubbin of hydrogen encased in diamond.

The laser beams entered at the top and bottom of the cylinder, vaporizing it. That generated an inward onslaught of X-rays that compresses a BB-size fuel pellet of deuterium and tritium, the heavier forms of hydrogen.

In a brief moment lasting less than 100 trillionths of a second, 2.05 megajoules of energy — roughly the equivalent of a pound of TNT — bombarded the hydrogen pellet. Out flowed a flood of neutron particles — the product of fusion — which carried about 3 megajoules of energy, a factor of 1.5 in energy gain.

This crossed the threshold that laser fusion scientists call ignition, the dividing line where the energy generated by fusion equals the energy of the incoming lasers that start the reaction.

“You see one diagnostic and you think maybe that’s not real and then you start to see more and more diagnostics rolling in, pointing to the same thing,” said Annie Kritcher, a physicist at Livermore who described reviewing the data after the experiment. “It’s a great feeling.”

The successful experiment finally delivers the ignition goal that was promised when construction of the National Ignition Facility started in 1997. When operations began in 2009, however, the facility hardly generated any fusion at all, an embarrassing disappointment after a $3.5 billion investment from the federal government.


----------

In an interview, Mark Herrmann, program director for weapons physics and design at the Livermore, said the researchers then performed a series of experiments to better understand the surprising August success, and they worked to bump up the energy of lasers by almost 10 percent and improve the design of the hydrogen targets.

The first laser shot at 2.05 megajoules was performed in September, and that first try produced 1.2 megajoules of fusion energy. Moreover, analysis showed that the spherical pellet of hydrogen was not squeezed evenly, and some of the hydrogen essentially squirted out the side and did not reach fusion temperatures.

The scientists made some adjustments that they believed would work better.

“The prediction ahead of the shot was that it could go up a factor of two,” Dr. Herrmann said. “In fact, it went up a little more than that.”

The main purpose of the National Ignition Facility is to conduct experiments to help the United States maintain its nuclear weapons. That makes the immediate implications for producing energy tentative.

Fusion would be essentially an emissions-free source of power, and it would help reduce the need for power plants burning coal and natural gas, which pump billions of tons of planet-warming carbon dioxide into the atmosphere each year.

But it will take quite a while before fusion becomes available on a widespread, practical scale, if ever.

Riaz Haq said…
Green investment on rise, Pakistan to get 30 % renewable energy - Pakistan Observer

https://pakobserver.net/green-investment-on-rise-pakistan-to-get-30-renewable-energy/


Until now, renewable energy sources make up a very minor fraction of Pakistan’s overall power generation mix. According to a recent report of the National Electric Power Regulatovry Authority, the installed capacity for wind and solar accounts for roughly 4.2% (1,831 MW) and 1.4% (630 MW) of a total of 43,775 MW, respectively.

China is already the biggest investor in green energy in Pakistan. Currently, out of the $144 million in foreign investment in solar PV plants in Pakistan, $125 million is from China, accounting for nearly 87% of the total.

Thanks to Chinese investments, a few weeks ago Federal Power Minister Khurram Dastgir Khan inaugurated two new wind energy projects in Jhimpir, Thatta District, Sindh, with an aim to produce cheaper and clean electricity through indigenous energy sources. Wind projects in this region have been one of several renewable energy projects to have received Chinese investment in recent years. Around 90 kilometers from Karachi, Jhimpir is the heartland of the country’s largest ‘Wind corridor’, which has the potential to produce 11,000 megawatts (MW) of energy from green resources.

Riaz Haq said…
Gwadar Pro Official
@Gwadar_Pro

China state-affiliated media
The Chinese company is working 24 hours a day according to three shifts on Dasu Hydropower Project. After the completion of Dasu Dam project, 4320 MW electricity will be generated. Thousands of employment opportunities have already been created on the project.

https://twitter.com/Gwadar_Pro/status/1610941378862940160?s=20&t=Skr5PQ-x7X-8EiVxL2GqMg

-----------

Wapda, KP districts sign deal to build transmission line


https://www.dawn.com/news/1726085


The Water and Power Development Authority (Wapda) and a united jirga from three districts in Khyber Pakh­tunkhwa’s Kohistan region signed an agreement on Monday to facilitate the construction of a transmission line for evacuation of 4,300 megawatts electricity to be generated by Dasu dam and other hydropower projects.

The “Confidence-Buil­ding Mea­s­ures’ Agree­ment (CBMA) was sig­ned between Wapda, the ad­­m­inistration of Hazara division, and notables from the three districts — Upper Kohistan, Lower Kohis­tan and Kolai Palas Kohistan.

Under the agreement, Wapda committed to implementing development schemes — to be selected through a yet to be conducted field survey — as CBMs under its Corporate Social Responsibility (CSR) in consultation with the civil administrations and the locals, Wapda said in a statement.

“Most importantly, this agreement will pave the way for smooth execution and completion of long-delayed 132kV transmission line from Duber hydel power station to Dasu, direly needed for stable supply of electricity during peak construction period of Dasu project,” it added.
Riaz Haq said…
#China, #Pakistan mark completion of #Karachi 2&3 (K2 & K3) #nuclear #power plants, each generating 1100 MW. "Since entering commercial operation, the K-2 and K-3 units have generated nearly 20 billion kilowatt-hours of #electricity" #Infrastructure https://www.world-nuclear-news.org/Articles/China,-Pakistan-mark-completion-of-Karachi-2-3-pro

A ceremony has been held to mark the inauguration of unit 3 of the Karachi nuclear power plant in Pakistan. China National Nuclear Corporation (CNNC) said the two Hualong One reactors at the site have now both officially been delivered to Pakistan and put into operation.


During the event, speeches were made by Pakistan's Prime Minister Shabaz Sharif, Pakistan Atomic Energy Commission Chairman Ali Raza, China Atomic Energy Agency Deputy Director Liu Jing and CNNC General Manager Gu Jun. International Atomic Energy Agency Director General Rafael Mariano Grossi also delivered a speech via video.

"Since entering commercial operation, the K-2 and K-3 units have generated nearly 20 billion kilowatt-hours of electricity, effectively alleviating the power shortage in Pakistan, as well as making positive contributions to Pakistan's social and economic development, energy security and independence, and addressing climate change," CNNC said. "At the same time, the K-2/K-3 project has provided more than 60,000 jobs for the local people throughout the whole cycle and trained a large number of local industrial workers."

Units 2 and 3 of the Karachi site - near Paradise Point in the province of Sindh - are the first exports of CNNC's 1100 MWe Hualong One pressurised water reactor, which is also promoted on the international market as HPR1000.

Construction of unit 2 began in 2015, with that of unit 3 following in May 2016. Karachi 2 achieved first criticality in February 2021 and was connected to the grid the following month after the completion of commissioning tests. The then Prime Minister Imran Khan formally inaugurated unit 2 on 21 May 2021.

Unit 3 achieved first criticality on 21 February 2022 and was connected to the grid on 4 March. Unit 3 passed acceptance tests on 18 April 2022, marking its entry into commercial operation.

According to CNNC, since Karachi units 2 and 3 have been put into operation, "the frequency and duration of local power outages have been greatly reduced".

The company noted Karachi 2 and 3 now provide Pakistan with nearly 20 billion kWh of clean electricity every year, meeting the annual demand of the local population of 2 million people. The units will reduce the equivalent standard coal consumption by 6.24 million tonnes per year, thereby cutting carbon dioxide emissions by 16.32 million tonnes.

The Karachi site - also sometimes referred to as KANUPP - was home to Pakistan's first nuclear power reactor, Karachi 1 - a small 100 MWe (90 MWe net) Canadian pressurised heavy water reactor which shut down in 2021 after 50 years of operation.

The first domestic demonstration plants of CNNC's Hualong One design are Fuqing 5 and 6, in China's Fujian province. The units entered commercial operation in January 2021 and March this year, respectively
Riaz Haq said…
POWERCHINA Celebrates 10th Anniversary of CPEC: Committed to Bringing Pakistan Forward for Green and Sustainable Development


https://www.businesswire.com/news/home/20230306005420/en/POWERCHINA-Celebrates-10th-Anniversary-of-CPEC-Committed-to-Bringing-Pakistan-Forward-for-Green-and-Sustainable-Development

This year will see the 10th anniversary of the China-proposed Belt and Road Initiative (BRI) and the 10th anniversary of the launch of the China–Pakistan Economic Corridor (CPEC). As one of the key enterprises participating in the construction of the CPEC, POWERCHINA has been active in various fields such as energy, electricity, water management, and infrastructure investment in Pakistan since it entered the Pakistani market as early as 1987.

Over the past 36 years, POWERCHINA has completed the 103 projects in Pakistan, including the first roller-compacted concrete (RCC) dam in Pakistan – the Gomal Zam Dam multipurpose project, and the first mainstream hydropower station on the Indus River – the Ghazi-Barotha Hydropower Project, the largest installed hydropower station – the Tarbela 4th & 5th Extension Hydropower Project, and the largest wind farm – the Tricon Boston 150 MW Wind Power Project.

In the past ten years, among the first 20 energy and infrastructure projects of the CPEC, POWERCHINA has participated in the investment and construction of 11 projects. POWERCHINA has consolidated the traditional power business, and continued to contribute to the development of new energy and other fields. Pakistan's largest hydropower hub project currently being constructed by POWERCHINA, the Diamer Basha Dam Project, will become the tallest and largest RCC dam in the world, and is expected to provide Pakistan with 18.1 billion KWh of clean electricity every year. As the project progresses, it is expected to provide more than 20,000 job opportunities, which is considered as one of the many positive effects of the project by Nadeem Ilyas, a Pakistani engineer of the project.

As one of the leading enterprises in China, POWERCHINA has carried out high-quality clean energy project construction and operation in accordance with international standards, and is committed to improving Pakistan's infrastructure conditions and alleviating local power shortages. It has not only made important contributions to the sustainable development of Pakistan, but also played a key role in the development of CPEC.
Riaz Haq said…
Pakistan has an energy surplus. Here’s why it gets hit by blackouts anyway
For several years, Pakistan’s cities and villages have suffered from power outages lasting several hours a day. In January, a nationwide blackout plunged the country of 230 million people into darkness. But the problem isn’t energy supply.

https://www.cnbc.com/video/2023/03/06/whats-behind-pakistans-energy-blackouts-and-power-outages.html

This January, much of Pakistan’s population of nearly 230 million people plunged into darkness, bringing widespread disruption to people and industries for almost 24 hours.

“If you go to our government hospitals – which didn’t have back-up facilities – or field hospitals, or small nursing homes, they had to stop all their services,” said Dr. Shayan Ansari, a surgeon at a private hospital in Pakistan’s capital, Islamabad.

A similar incident struck last October. Meanwhile, smaller blackouts regularly hit cities and villages for several hours daily.

But the problem is not energy supply.

“We don’t have a problem as far as the supply of energy is concerned in Pakistan,” said Ishrat Husain, who served as an advisor to ex-Prime Minister Imran Khan. “Both outages were caused because there were fluctuations on the transmission lines, which have not been updated for quite some time.”

In 2020, nearly 20 percent of Pakistan’s energy was simply lost during transmission, distribution and delivery.

Pakistan’s energy problems are having a cascading effect on the country’s economy, which is on the verge of collapse. Watch the video above to find out more.

Riaz Haq said…
India's power output grows at fastest pace in 33 years, fuelled by coal

https://www.livemint.com/news/india/indias-power-output-grows-at-fastest-pace-in-33-years-fuelled-by-coal-11680738025627.html

Fossil fuel-fired power output rises fastest in nearly 3 decades
Emissions from power gen rose nearly a sixth to 1.15 bln tonnes
Coal-fired power output up 12.4%, gas-fired output down 29%
Share of coal in overall power output rose to 73.1%
Renewables output rose 21.7%, share up to 11.8%


The rise in power demand due to intense summer heatwaves, a colder-than-usual winter in northern India, and an economic recovery compelled India to increase its power output from coal plants and solar farms, preventing power cuts.

An analysis of daily load data from regulator Grid-India showed that power generation in India increased by 11.5% to 1,591.11 billion kilowatt-hours (kWh) in the fiscal year ending in March 2023. This rise in power generation was the highest since the year ending March 1990.

The analysis revealed that fossil-fuel-based plants witnessed an 11.2% growth, the highest in over 30 years, with coal-fired plants recording a 12.4% surge in electricity production, compensating for a 28.7% decrease in cleaner gas-fired plant output due to high global liquefied natural gas (LNG) prices.

In the new fiscal year that began April 1, Indian power plants are expected to burn about 8% more coal.

The rapid acceleration in India's coal-fired output to address a spike in power demand underscores challenges faced by the world's third largest greenhouse gas-emitter in weaning its economy off carbon, as it attempts to ensure energy security to around 1.4 billion Indians.

Total power supplied during the last fiscal year was 1509.15 billion kWh, 8.4% higher than a year earlier but still 6.69 billion units short of demand, the widest deficit in six years.


Electricity generated from coal rose to 1,162.91 billion kWh, the data showed, with its share in overall output rising to 73.1% - the highest level since the year ending March 2019.

India's Central Electricity authority estimates that 1 million kWh of power produced from coal generates 975 tonnes of carbon dioxide, while the same amount of power generated from gas produces 475 tonnes. A plant fired by lignite, known as brown coal, emits 1,280 tonnes to produce equivalent power.

RENEWABLES PUSH

Increased fossil fuel burning for power in the world's fifth largest economy drove up CO2 emissions during the year by nearly a sixth, to 1.15 billion tonnes, Reuters calculations based on government data and emissions estimates show.

That is 3.4% of the International Energy Agency's estimate of annual global emissions of 33.8 billion tonnes in 2022.

Many major countries boosted coal use in the twelve months due to Russia's invasion of Ukraine, but the rise was steepest in India, data from energy think-tank Ember shows.

The government has defended India's high coal use citing lower per capita emissions compared with richer nations and rising renewable energy output.

After missing a target to install 175 GW in renewable energy capacity by 2022, India is trying to boost non-fossil capacity - solar and wind energy, nuclear and hydro power, and bio-power - to 500 GW by 2030.

During the fiscal year that recently ended, India's solar capacity additions increased by 20%, leading to a record increase of 33.3 billion units or 21.7% in renewable energy output to 187.1 billion units, as per data analysis.

The significant rise in green energy output prevented 32.5 million tonnes of CO2 emissions that would have otherwise resulted from coal-fired power generation.

The data also revealed that the share of renewables in power generation, excluding large hydro and nuclear power, increased from 10.8% to 11.8% in 2022/23, primarily due to a 35% rise in solar output.

Riaz Haq said…
Saudi Arabia signs $240m loan agreement to support Mohmand Dam

https://www.dawn.com/news/1746406/saudi-arabia-signs-240m-loan-agreement-to-support-mohmand-dam

The statement noted that the project is expected to enhance water and food security, and improve the standard of living for people in Khyber Pakhtunkhwa, where almost 80 per cent of the population resides in rural areas, boosting the region’s socioeconomic development by creating employment opportunities and reducing poverty levels.

It added that by using renewable energy sources, the project will generate 800 MW of electricity production capacity, contributing to Pakistan’s energy security. In addition, the storage of 1.6 million cubic meters of water will support sustainable agricultural practices, enable irrigation of 6,773 hectares of new land, and increase the total cropping area from 1,517 hectares to 9,227 hectares in the province, facilitating agricultural activities.

Co-financed by the SFD, OPEC, Islamic Development Bank, and the Kuwait Fund for Arab Economic Development, the project aligns with SDG-2 (Food Security), SDG-6 (Clean Water), and SDG-7 (Clean Energy) and embodies SDG-17 (Partnerships for the Goals).

During the agreement signing ceremony, the CEO of SFD said this initiative is an extension of the fund’s continued support for development projects and programmes in Pakistan since its inception. He also highlighted the significance of joint cooperation between development funds, as evidenced by this project.

For his part, Dr Niaz expressed his sincere appreciation and gratitude to the Kingdom of Saudi Arabia for its unwavering support towards the development sector in Pakistan through the SFD.
Riaz Haq said…
#Pakistan #Hydro #power: 1530MW #Tarbela 5th Extension Project to start power generation in 2025. It's financed by World Bank ($390 million) and Asian Infrastructure Investment Bank ($300 million). #RenewableEnergy #electricity https://www.nation.com.pk/20-May-2023/1530mw-tarbela-5th-extension-project-to-start-power-generation-in-2025 via @the_nation

Tarbela 5th Extension Hydropower Project, having a cumulative generation capacity of 1530MW, will start power generation in 2025.

While briefing Chairman WAPDA Engr Lt Gen (r) Sajjad Ghani during his visit to Tarbela 5th Extension Hydropower Project, it was informed that electricity generation from the project would start in 2025. Masood Ahmed from World Bank also accompanied the chairman. GM Tarbela Dam Zakir Ateeq, PD Tarbela 5th Extension Hydropower Project and representatives of the consultants and the contractor, made detailed presentation on progress of the project. It was briefed that construction activities are underway on five sites. Recovery plan to match the completion schedule of the project was also discussed in detail during the briefing.

Earlier, the chairman witnessed construction work on various sites including intake, penstock and outlet, power house, tailrace culvert and switch yard. Member (Power) WAPDA Jamil Akhtar, GM (Power) Tarbela Nasrum Minallah, GM (HRD) Brig Hamid Raza (Retd) and GM (Security) Brig Muhammad Tufail (Retd) were also present on the occasion.

During his interaction with the project management, the chairman said that green, clean and affordable hydel electricity is all the more important to rationalise the tariff and stabilise the economy. This necessitates timely completion of hydropower projects, he added. The Chairman urged the project management to gear up their efforts and complete Tarbela 5th Extension Hydropower Project in accordance with the schedule.

WAPDA is constructing Tarbela 5th Extension Hydropower Project on Tunnel No. 5 of Tarbela Dam. World Bank and Asian Infrastructure Investment Bank (AIIB) are providing financial assistance for the project to the tune of $390 million and $300 million respectively. Cumulative generation capacity of the project stands at 1530MW with three generating units of 510MW each. The project will provide 1.347 billion units of environment friendly and low-cost hydel electricity to the national grid on the average every year. With completion of Tarbela 5th Extension Project, installed capacity at Tarbela Dam will increase from 4888 MW to 6418 MW. Chairman WAPDA also visited intake structure of Tarbela 4th Extension Hydel Power Station and discussed operation and maintenance (O&M) activities of the power station. Commissioned in 2018 with funding of the World Bank, the 1410 MW-Tarbela 4th Extension Hydel Power Station has so far provided 18.67 billion units of electricity to the national grid.
Riaz Haq said…
CPEC Suki Kinari project nears completion | The Manila Times

https://www.manilatimes.net/2023/06/12/business/foreign-business/cpec-suki-kinari-project-nears-completion/1895652

The Suki Kinari Hydropower project in northwest Pakistan achieved the hoisting of a core component on Saturday, as a 413-ton rotor, crucial to turning water into electricity, was smoothly installed on the last of four generating units.

The successful hoisting of the last rotor will help advance the construction progress of the power station under the China-Pakistan Economic Corridor (CPEC), located in the Mansehra district of the South Asian country's Khyber Pakhtunkhwa province.

Noting the hoisting of the last rotor as a key milestone of the 884-megawatt hydropower project, Yu Zhiliang, assistant general manager of the Suki Kinari Hydropower project of the Overseas Investment Co. of China Gezhouba Group, which invests in and implements the project, said that it marks the installation of the unit body of the hydropower station is coming to an end.

It is also a solid step for the waterless commissioning of four generating units in the coming six months, said Yu.

The hydropower project started construction in January 2017. Once getting functional, the CPEC project will annually generate some 3.21 billion kilowatt-hours of clean electricity, replacing 1.28 million tons of coal and reducing 2.52 million tons of carbon dioxide emissions per year, said Yu.



It will significantly optimize Pakistan's energy structure, boosting the country's economic and social development, he added.

Launched in 2013, the CPEC is a corridor linking Pakistan's Gwadar port with Kashgar in northwest China's Xinjiang Uygur Autonomous Region, highlighting energy, transport and industrial cooperation.

Riaz Haq said…
Pakistan will add up to 10 GW of new hydropower capacity by 2030 | Enerdata

https://www.enerdata.net/publications/daily-energy-news/pakistan-will-add-10-gw-new-hydropower-capacity-2030.html

In July 2022, Pakistan commissioned the 720 MW Karot hydropower plant, one of five projects on the Jhelum River (northern Pakistan), alongside the Azad Pattan plant (700 MW), the Mangla Dam (1.1 GW), the Neelum-Jehlum plant (969 MW) and the Kohala plant (1.1 GW).

----------

700MW Azad Pattan hydropower project ready for construction: Energy China - Profit by Pakistan Today

https://profit.pakistantoday.com.pk/2023/06/14/700mw-azad-pattan-hydropower-project-ready-for-construction-energy-china/

Wang Huihua, Managing Director of China Energy Int’l Group’s Pakistan Branch, announced that the 700-megawatt Azad Pattan hydropower project, run by Energy China, is ready for construction after the completion of a feasibility study and land acquisition.

Wang made these remarks at the ‘Pakistan Energy Sector Landscape: Challenges & Opportunities’ conference held at NUST University, Islamabad.

He explained that the project would provide cheap, clean energy to Pakistan. “We have been developing this project for six years. We hope the government will give it more priority in the China-Pakistan Economic Corridor (CPEC) initiative to expedite financial closure,” he said.

He further stated that Energy China believed that investing in renewable energy in Pakistan was financially viable. “We are committed to setting up our long-term operation in Pakistan and investing more,” he said.

He highlighted that China Energy Engineering Corp. (Energy China) has been present in Pakistan for the past 20 years. “Energy China considers Pakistan as its favored investment destination,” he added.

Wang also pointed out some of the challenges faced by foreign investors in Pakistan, underscoring the importance of resolving them quickly to foster win-win cooperation.
Riaz Haq said…
#Pakistan and #China sign $4.8 billion 1200 MW #nuclear #power plant deal. Work on Chashma 5 project would begin immediately. China's support will help Pakistan make the transition away from reliance on #FossilFuels . #nuclearenergy #electricity
https://www.reuters.com/business/energy/pakistan-china-sign-48-bln-nuclear-power-plant-deal-2023-06-20/

Pakistan and China signed a $4.8 billion deal on Tuesday to build a 1,200-megawatt nuclear power plant, Prime Minister Shehbaz Sharif said, hailing the investment by a country that Pakistan views as its most dependable ally.

Work on the Chashma 5 project would begin immediately, Sharif said on state-run news channel PTV following the signing of the memorandum of understanding (MOU) between China National Nuclear Cooperation and Pakistan Atomic Energy Commission.

"Investment from China in this project to the tune of $4.8 billion sends a message loud and clear that Pakistan is a place where Chinese companies and investors continue to show their trust and faith," Sharif said.

The Chashma 5 project will be built in the central province of Punjab. China's support will help Pakistan make the transition away from reliance on fossil fuels.

Pakistan's total nuclear energy production capacity rose to 1,400 mw, when the country's sixth nuclear power plant opened two years ago. Located in the southern port city of Karachi, that 1,100 mw plant was also constructed with Chinese assistance.

Sharif, whose government is desperately struggling to stave off a balance of payments crisis, thanked the Chinese partners for offering a $100-million discount for the latest project.

It is unclear whether the new investment is part of the $65 billion that China has pledged in infrastructure building for Pakistan under its Belt and Road Initiative.

The new project was originally planned to start a couple of years ago, and Sharif expressed thanks to the Chinese side for not rescheduling costs despite the long delay. Instead, he said, the Chinese had disbursed an initial 30 billion Pakistani rupees ($104.53 million) to start the project.
Riaz Haq said…
Pakistan Expanding Nuclear Plant With New Hualong One Reactor

https://www.powermag.com/pakistan-expanding-nuclear-plant-with-new-hualong-one-reactor/


By Darrell Proctor is a senior associate editor for POWER (@POWERmagazine).

China continues to be a world leader in exporting its nuclear power technology. Chinese officials in Pakistan on June 20 signed a memorandum of understanding (MOU) for a $4.8 billion deal with Pakistan’s nuclear energy agency for construction of a new 1,200-MW reactor at the Chashma power complex.

The new unit will be China’s Hualong One, or HPR1000, pressurized water reactor technology.

Pakistan Prime Minister Shehbaz Sharif on Tuesday said the country considers China its “most dependable ally.” Sharif, whose country is in the midst of an economic crisis and looking for outside investment in its energy sector, said construction of the Chashma 5 project, located in Punjab province, would begin immediately.

The Chashma complex has four CNP-300 reactors currently in operation, each with 325 MW of generation capacity. The units were developed by China National Nuclear Corp. (CNNC). The first unit came online in 1991; the other units entered commercial operation in 2011, 2016, and 2017, respectively.

Chashma 5 will be built by CNNC subsidiary CNNC China Zhongyuan Engineering Corp., the company said.

Chinese officials recently announced that an HPR1000 has also been proposed for construction at the Bradwell site in the UK. Britain’s Office for Nuclear Regulation and the Environment Agency said they have started a second, technical, phase of the assessment program for the HPR1000.

Chinese Investment
Sharif, speaking Tuesday on Pakistan’s state-run news channel PTV after the signing of the MOU between the Pakistan Atomic Energy Commission and Chinese officials, said, “Investment from China in this project to the tune of $4.8 billion sends a message loud and clear that Pakistan is a place where Chinese companies and investors continue to show their trust and faith.”

The prime minister originally brokered the project during his time as chief minister of Punjab, an office he held three times, most recently from 2013 to 2018. He was elected as Pakistan’s prime minister in April 2022.

Sharif has supported nuclear power as a way to move Pakistan away from fossil fuels. Its most recent nuclear facility, the 2,200-MW Karachi Nuclear Power Plant, also known as KANUPP, in the southern port city of Karachi, commissioned its two reactors in 2021 and 2022, respectively. That facility, featuring two Hualong One Generation III pressurized water reactors, also was built with financial backing from China.

Sharif on Tuesday said the Chashma 5 project was originally planned to start in 2021. He said Chinese officials did not raise the cost of the project from original estimates despite the delay. Officials on Tuesday said China has to date disbursed 30 billion Pakistani rupees ($104.53 million) to start the project.

“We are deeply obliged to [China] President Xi Jinping, and the Chinese leadership for their generous help to Pakistan,” Sharif said. He also recognized Saudi Arabia, United Arab Emirates and Qatar for extending financial support to Pakistan’s government.

Pakistan for years has contended with power outages. Two of the worst incidents occurred in January 2021, and again in January of this year. In 2021, a fault at a power plant brought down the national grid, leading to calls for a massive overhaul of the country’s electricity transmission infrastructure.

A nationwide power outage on Jan. 30 of this year impacted all of Pakistan’s major cities and left millions of people without electricity.


Riaz Haq said…
Pakistan Signs $4.8 Billion Nuclear Power Plant Deal With China

https://www.voanews.com/a/pakistan-signs-4-8-billion-nuclear-power-plant-deal-with-china/7144967.html


Pakistan and China signed a $4.8 billion deal Tuesday to build what would be the seventh Chinese nuclear power plant in the South Asian nation.

The 1,200-megawatt project will be installed in the central Pakistani city of Chashma, where Beijing already has built four nuclear power generation units with a collective output of nearly 1,230 megawatts.

Prime Minister Shehbaz Sharif oversaw Tuesday's signing of the memorandum of understanding between China National Nuclear Cooperation and the Pakistan Atomic Energy Commission.

According to the agreement, the Chinese company will employ its HPR 1000 technology, known as HPR1000 or Hualong One, to construct the nuclear power unit. It will be the third facility in Pakistan to feature the HPR 1000, or pressurized water reactor technology.

"Investment from China in this project to the tune of $4.8 billion sends a loud and clear message that Pakistan is a place where Chinese companies and investors continue to show their trust and faith," Sharif said.

He thanked Beijing for offering a more than $100 million discount for what is named the Chashma 5 power plant. The work on the project was initially planned to start a couple of years ago, but Sharif said the Chinese partners had not rescheduled costs despite the long delay.

"This project is part of our energy security plan to diversify the energy mix with a focus on ensuring the provision of cheap electricity to the industry & relief to the common man,” the Pakistani prime minister wrote on Twitter after the ceremony.

Sharif's coalition government is struggling to deal with unprecedented economic challenges facing Pakistan, including a balance of payments crisis.

China has recently also constructed two nuclear power plants in the southern port city of Karachi, each with a 1,100-megawatt generation capacity.

Pakistani officials say the two Chinese-supplied third-generation Hualong One reactors, known as K2 and K3, cost roughly $10 billion. They are equipped with "advanced safety and foolproof security features" and have enhanced Pakistan's nuclear energy production to more than 3,500 megawatts.

"K2 and K3 are fully functional and supply 2,200 megawatts of electricity to the national grid. Similarly, nuclear power plants at Chashma are contributing more than 1,300 megawatts," a PAEC spokesman told VOA on Tuesday.

Canada helped Pakistan build its first nuclear power plant in 1972 in Karachi, producing about 80 megawatts of electricity. It is expected to be shut down soon after having served its purpose for about the full extent of the planned operation.

China maintains close defense and economic relations with staunch ally Pakistan. It has invested more than $20 billion in building road networks, power plants, and ports over the past decade under what is known as the China-Pakistan Economic Corridor, or CPEC.

Officials in both countries say the collaboration, an extension of Beijing's global Belt and Road infrastructure initiative, has created tens of thousands of jobs and ended Pakistan's crippling energy crisis.
Riaz Haq said…
Dasu Hydropower Project: Stage 1 of concrete Starter Dam completed


https://www.nation.com.pk/22-Jun-2023/dasu-hydropower-project-stage-1-of-concrete-starter-dam-completed

In a major development towards implementation of Dasu Hydropower Project, Stage 1 of the concrete Starter Dam has been completed upstream of Main Dam site.

As per the design, the Starter Dam for Dasu Hydropower Project is to be completed in two stages; Stage 1 up to elevation of 785 meters while Stage 2 up to elevation of 798 meters above mean sea level, said a spokesperson WAPDA here. The Stage 1 of the concrete Starter Dam was completed in June this year before the high flow season – a major landmark which the project team successfully achieved, the spokesperson said.

As the high flow season has started, River Indus is flowing through the two diversion tunnels completed earlier this year, while some of the river water is overtopping the concrete Starter Dam as designed.

After the high flow season in October this year, the construction of the Starter Dam’s Stage 2 will be carried out. The Stage 2 is scheduled for completion during the coming low flow season. The project is being constructed across the River Indus, upstream of Dasu Town in Upper Kohistan district of Khyber Pakhtunkhwa. The 4,320-MW-Dasu Hydropower Project is planned to be completed in two stages. At present, WAPDA is constructing its stage-I with installed generation capacity of 2,160-MW and annual energy generation of 12 billion units. Stage-I of the project is likely to start electricity generation in 2026. The 2,160-MW stage-II, when implemented, will also provide 9 billion units to the national grid. On completion of the both stages, Dasu will become the project with highest annual energy generation in Pakistan i.e. 21 billion units per annum on the average. The project will commence by end 2026. It is worth mentioning here that in February this year, Dasu Hydropower Project crossed a major milestone as the River Indus was successfully diverted following completion of a 1.33-kilometre long diversion tunnel.


Following the completion of one of the two diversion tunnels, the River Indus was successfully diverted to the completed tunnel. Instead of its natural course, the River Indus is now flowing through a 1.33-kilometer long diversion tunnel with 20-metre width and 23-metre height. Consequently, construction activities have been initiated on the starter dam, leading towards construction of the main dam of Dasu Hydropower Project.

Riaz Haq said…
Pakistan’s PM Shehbaz Sharif launches US$3.5 billion Chinese-designed nuclear energy project

https://www.scmp.com/news/asia/south-asia/article/3227776/pakistans-pm-sharif-launches-us35-billion-chinese-designed-nuclear-energy-project

The two countries had already signed an agreement to construct a state-of-the-art Hualong One reactor
China also gave US$5 billion loan to Pakistan to help it unlock a bailout from the IMF



Pakistan’s Prime Minister Shehbaz Sharif on Friday launched the construction of a 1,200-megawatt Chinese-designed nuclear energy project, which will be built at a cost of US$3.5 billion as part of the government efforts to generate more clean energy in the Islamic nation.
The ceremony to mark the project’s start comes less than a month after Pakistan signed an agreement with China’s National Nuclear Corporation Overseas in the capital, Islamabad, to construct a Hualong One reactor – a third-generation nuclear reactor and is considered safer because of the latest security features.
Pakistan and China are long-time allies. Pakistan’s relations with Beijing are so close that its leadership calls China their “Iron Brother.” China is also building roads, bridges, power plants, and railways to link its far west with the Chinese-built port of Gwadar on the Indian Ocean.

Riaz Haq said…
China Begins Construction of Pakistan's Largest Nuclear Power Plant

https://www.voanews.com/a/china-begins-construction-of-pakistan-s-largest-nuclear-power-plant-/7181016.html


Pakistan held a groundbreaking ceremony Friday for what will be its largest civil nuclear power plant — constructed by China — that will contribute 1,200 megawatts of electricity daily to the national grid and is estimated to cost at least $3.5 billion.

Prime Minister Shehbaz Sharif and senior Chinese officials attended the televised event in the central city of Chashma, dubbed the birthplace of China-Pakistan nuclear energy cooperation.

Over the past 30 years, Beijing has installed four nuclear power generation units in Chashma, collectively generating about 1,300 megawatts, with China providing enriched uranium for fuel.

"This mutual cooperation to promote clean, efficient, and comparatively cheaper energy is a gift of friendship between the two countries and a model for other countries to emulate," Sharif said at the ceremony.

The plant, known as Chashma-5, or C-5, will feature what China says is its domestically developed third-generation pressurized water nuclear technology, the Hualong One or HPR1000, with "advanced safety and foolproof security features."

Raja Ali Raza, the head of the Pakistan Atomic Energy Commission, said the nuclear plant project will be completed by 2030.

"C-5 will be Pakistan's largest generation-III plus nuclear power project," Raza said. "This project has brought PAEC one step closer to its envisaged goal of production of 8,800 megawatts electric cheap and clean energy."

Beijing has previously supplied the HPR1000 technology for two nuclear power stations, each with a 1,100-megawatt generation capacity, built and operationalized in the last couple of years in the southern port city of Karachi, enhancing Pakistan's nuclear energy production to more than 3,500 megawatts a day.

Analysts see China's accelerated civil nuclear cooperation with Pakistan as part of efforts to globally find more lucrative buyers for its HPR1000 reactors developed by state-owned China National Nuclear Corporation or CNNC, the country's second-largest nuclear power producer company.


"HPR1000 is a homegrown nuclear technology of CNNC and a flagship of China's advanced equipment manufacturing," Yu Jianfeng, the CNNC chairman, told the ceremony. He noted that more than 17 units of HPR1000 are currently under construction in China.

"Today's groundbreaking for the C-5 project is a significant milestone for HPR1000's global journey and a new start for the China-Pakistan nuclear energy cooperation," Yu stated. "Our cooperation in nuclear energy has become an integral part of the China-Pakistan all-weather strategic cooperative partnership and a shining example of international nuclear energy cooperation."

Under its global Belt and Road Initiative, Beijing also has built and put into commercial operation 14 mostly coal-fired power plants in Pakistan in the last 10 years, with a total installed capacity of 8,000 megawatts daily.

The projects are part of the China-Pakistan Economic Corridor, or CPEC, which has also built road networks, highways, ports, and industrial zones with direct Chinese investment and "soft loans," expected to increase to about $62 billion by 2030 when the mega undertaking is due to be complete.

Critics blame CPEC for contributing to Pakistan's deepening economic troubles and depleting foreign exchange reserves, making it difficult for the country to catch up with its foreign debt repayments.

Pakistan owes more than $1.3 billion (350 billion rupees) to Chinese power plants. The amount keeps growing, and China has refused to defer or restructure the payment and CPEC debt repayments.

Popular posts from this blog

Pakistani Women's Growing Particpation in Workforce

Project Azm: Pakistan to Develop 5th Generation Fighter Plane

Pakistan's Saadia Zahidi Leads World Economic Forum's Gender Parity Effort